# 362100354257
Unscheduled inspection
Start date: 2021-07-20, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This inspection is carried out in order to implement the program of inspections during the construction of a capital construction facility, developed on the basis of a notice of the beginning of construction (reconstruction).
The objectives of this audit are: prevention, detection and suppression of violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction (reconstruction) on the basis of an agreement with the developer or the technical customer.
The subject of this audit is: compliance with mandatory requirements or requirements established by municipal legal acts.
# 362004459377
Unscheduled inspection
Start date: 2020-07-22, end date: 2020-08-18, duration: —
Authority: Gosudarstvennaya inspekciya truda v Voronezhskoi oblasti
Purpose of inspection: implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms in accordance with Rostrud Order No. 07022020 29 issued on the basis of instructions from Deputy Prime Minister of the Russian Federation Tatyana Golikova dated December 27, 2019 TG 1211486
# 361902810593
Unscheduled inspection
Start date: 2019-06-25, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection:
# 361902643746
Unscheduled inspection
Start date: 2019-04-15, end date: 2019-04-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the start of construction reconstruction The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The purpose of the audit is to comply with mandatory requirements or requirements established by municipal legal acts
# 361800277111
Unscheduled inspection
Start date: 2018-04-17, end date: 2018-04-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer The subject of this audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 36170801941075
Unscheduled inspection
Start date: 2017-08-30, end date: 2017-09-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The verification is compliance with mandatory requirements or requirements established by municipal legal acts
# 36170701424422
Unscheduled inspection
Start date: 2017-03-27, end date: 2017-04-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The verification is compliance with mandatory requirements or requirements established by municipal legal acts
# 36160701071179
Unscheduled inspection
Start date: 2016-10-27, end date: 2016-11-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer. The verification is compliance with mandatory requirements or requirements established by municipal legal acts