# 771902994501
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Proverka provoditsya s celyu Zaschity prav i interesov rabotnikov v svyazi s rassmotreniem obrascheniya ot 08072019 7772250819OB po voprosam narusheniya trudovogo zakonodatelstva Zadachami proverki yavlyayutsya nadzor i kontrol za soblyudeniem zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami sootvetstvie svedenii soderzhaschihsya v uvedomlenii o nachale osuschestvleniya otdelnyh vidov predprinimatelskoi deyatelnosti obyazatelnym trebovaniyam sootvetstvie svedenii soderzhaschihsya v zayavlenii i dokumentah yuridicheskogo lica ili individualnogo predprinimatelya o predostavlenii pravovogo statusa specialnogo razresheniya licenzii vydachi razresheniya soglasovaniya obyazatelnym trebovaniyam a takzhe dannym ob ukazannyh yuridicheskih licah i individualnyh predprinimatelyah soderzhaschimsya v edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya provedenie meropriyatii po predotvrascheniyu prichineniya vreda zhizni zdorovyu grazhdan vreda zhivotnym rasteniyam okruzhayuschei srede obektam kulturnogo naslediya pamyatnikam istorii i kultury narodov Rossiiskoi Federacii muzeinym predmetam i muzeinym kollekciyam vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii dokumentam imeyuschim osoboe istoricheskoe znachenie nauchnoe kulturnoe znachenie vhodyaschim v sostav nacionalnogo bibliotechnogo fonda po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera po obespecheniyu bezopasnosti gosudarstva po likvidacii posledstvii prichineniya takogo vreda
# 34170802307057
Unscheduled inspection
Start date: 2017-09-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 34170801953916
Unscheduled inspection
Start date: 2017-08-28, end date: 2017-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: Cel ocenka sootvetstviya deyatelnosti osuschestvlyaemoi na Obekte trebovaniyam gradostroitelnogo zakonodatelstva Rossiiskoi Federacii zakonodatelstva Rossiiskoi Federacii v oblasti ohrany okruzhayuschei sredy trebovanii pozharnoi bezopasnosti i sanitarnoepidemiologicheskogo blagopoluchiya naseleniya v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiZadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva Rossiiskoi Federacii v tom chisle tehnicheskih reglamentov i proektnoi dokumentaciiPredmet vypolnenie predpisaniya ot 23 iyunya 2017 goda 4906 vydannogo OOO MKDStroi ob ustranenii narushenii dopuschennyh pri stroitelstve Obekta
# 34170701704157
Unscheduled inspection
Start date: 2017-06-15, end date: 2017-06-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The audit is carried out in order to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation, as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentationthe purpose of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation, including technical regulations and project documentationthe subject of this The purpose of the audit is to ensure compliance with mandatory requirements regarding the compliance of construction works, their results and the construction materials used with the requirements of technical regulations, project documentation, and the availability of a construction permit and compliance with established requirements for admission to construction work
# 34170701534680
Unscheduled inspection
Start date: 2017-04-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection:
# 34160701132073
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-11-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to comply with the activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation in including technical regulations and design documentationsubject compliance with mandatory requirements in relation to the compliance of construction works with their results and applied building materials with the requirements of technical regulations of design documentationand the availability of a construction permit and compliance with established requirements for admission to construction work