# 472004537333
Unscheduled inspection
Start date: 2020-08-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004415412
Unscheduled inspection
Start date: 2020-05-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004337114
Unscheduled inspection
Start date: 2020-03-04, end date: 2020-04-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 471904128807
Unscheduled inspection
Start date: 2019-12-18, end date: 2020-01-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification verification of the completion of work on the construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements including compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility and also, the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used meeting the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation