Found 5 inspections:

# 77180803274444
Unscheduled inspection
Start date: 2018-11-12, end date: 2018-12-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803152852
Unscheduled inspection
Start date: 2018-05-31, end date: 2018-06-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802705657
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160700856613
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Establishing the existence of a construction permit in accordance with ST51 of the Urban Planning Code of the Russian Federation, the absence of which poses a potential threat of harm to life, health, property or causing such harm based on the receipt of an application for unauthorized construction of a capital construction facility. The objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activity by the person being audited. The subject of this audit is the availability of a construction permit reconstruction


# 77160601769846
Unscheduled inspection
Start date: 2016-08-03, end date: 2016-08-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: To establish that this inspection is conducted in order to establish the existence of a construction permit in accordance with st51 of the Urban Planning Code of the Russian Federation, the absence of which poses a potential threat of harm to life, health, property or causing such harm on the basis of a request for unauthorized construction of a capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban planning activities by the person being audited. The real check is the availability of a construction and reconstruction permit


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.