Found 2 inspections:

# 661800617949
Unscheduled inspection
Start date: 2018-08-10, end date: 2018-08-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The audit is conducted in order to monitor the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 2918071121 dated May 21, 2018 with a deadline for eliminating violations 02082018 the objectives of this audit are to carry out regional state construction supervision The subject of this audit is the implementation of the previously issued order to eliminate the identified violation of mandatory requirements 2918071121 dated May 21, 2018


# 661800509145
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-12, duration:
Authority: Gosudarstvennaya inspekciya truda v Sverdlovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees in connection with the consideration of the appeal dated 13062018 667147418


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.