# 162004450539
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004396841
Unscheduled inspection
Start date: 2020-04-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004358286
Unscheduled inspection
Start date: 2020-03-13, end date: 2020-04-09, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Federal State supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms registration number of the function in the federal state information system "Federal Register of State and Municipal Services Functions" 10001244260 Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Written request from a citizen 167112920OB from 05032020
# 162004256846
Unscheduled inspection
Start date: 2020-02-05, end date: 2020-02-06, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 07082019 case 121120190094 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004256831
Unscheduled inspection
Start date: 2020-02-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161904020965
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the construction materials used in the construction of a capital construction facility with the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 07082019 121120190094 prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements and or requirements established by municipal legal acts
# 161903542715
Unscheduled inspection
Start date: 2019-09-17, end date: 2019-09-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation. in accordance with the inspection program dated 10012019 case 170420190001, the objectives of this inspection are to prevent, identify and prevent violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed by the developer, the customer, or the person carrying out construction on the basis of a contract with the developer or the customer. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902494353
Unscheduled inspection
Start date: 2019-02-08, end date: 2019-02-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of the fact of execution of the order dated 19122018 1219129802, the deadline for which expired on 31.012019, and drawing up an act based on the results of the inspection, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with the regulations of the authorities state control supervision of municipal control bodies
# 161902449067
Unscheduled inspection
Start date: 2019-01-25, end date: 2019-02-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: To establish that this inspection is carried out in order to establish compliance with the requirements of Part 5 of Article 52 of the Urban Planning Code of the Russian Federation, as well as to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. construction of compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notice received by the Inspectorate on the start of construction of the capital construction facility dated 09.01201954 The objectives of this inspection are to prevent as well as identify and suppress violations of compliance committed by the developer customer the person carrying out construction on the basis of a contract with the developer or the customer performed during the construction of the capital construction facility The subject of this audit is to select the necessary compliance with the mandatory requirements and or requirements established by municipal legal acts.
# 161802317369
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determination of compliance of the construction materials used in the construction of a capital construction facility with the results of such work with the requirements of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 23032018 case 121120160096 prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements and or requirements established by municipal legal acts
# 16160700812946
Unscheduled inspection
Start date: 2016-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160601780407
Unscheduled inspection
Start date: 2016-08-09, end date: 2016-08-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: to establish compliance with the requirements of part 5 of Article 52 of the Urban Planning Code of the Russian Federation on the basis of the notice received by the Inspectorate on the start of construction of the reconstruction of the capital construction facility dated 01082016 6371 warning, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations and other regulatory documents legal acts and project documentationcompliance with mandatory requirements or requirements established by municipal legal acts
# 16160700084030
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used during the construction and reconstruction of the capital construction facility comply with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, construction permits, and compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation. In accordance with the inspection program dated 01082016 case 121120160060the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of this inspection is to comply with mandatory requirements or requirements established by municipal authorities. legal acts
# 16160700084012
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate from 23082016 7218 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 10082016 1219070301 to 22082016G tasks The purpose of this audit is to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, while eliminating previously identified violations. The purpose of this audit is to comply with the instructions of state control bodies, municipal control bodies