# 621904120033
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-04, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: assessment of the conformity of the work performed
# 001902635742
Unscheduled inspection
Start date: 2019-03-25, end date: 2019-03-29, duration: —
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the execution of the order of the Federal Service for Environmental Technological and Nuclear Supervision dated February 01, 2019 44 "On conducting inspections of compliance with mandatory requirements by electric power industry entities, heat supply organizations and consumers of electric energy in 2019" issued on the basis of the instruction of the Government of the Russian Federation dated January 18, 2019 DKP9254 Tasks Prevention detection and suppression of violations of mandatory requirements prevention of accidents and injuries The subject is compliance with mandatory requirements of legislation and other regulatory acts in the field of electric power industry
# 621802183951
Unscheduled inspection
Start date: 2018-12-19, end date: 2018-12-21, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: verification of the conformity of installed 10 kV 04 kV power supply lines for outdoor electric lighting of the building materials used
# 621802183872
Unscheduled inspection
Start date: 2018-11-29, end date: 2018-12-03, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: checking the conformity of installed 10 kV 04 kV power supply lines for outdoor electric lighting
# 621802056226
Unscheduled inspection
Start date: 2018-11-12, end date: 2018-11-14, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Ryazanskoi oblasti
Purpose of inspection: verification of compliance of the completed works with the requirements of the project documentation