# 772101097145
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100620811
Unscheduled inspection
Start date: 2021-09-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100194022
Unscheduled inspection
Start date: 2021-04-29, end date: —, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: To establish that the purpose and objective of this audit is to verify compliance with the mandatory requirements of the legislation on participation in the shared-equity construction of apartment buildings and (or) other real estate objects.
The subject of an unscheduled documentary check is compliance with the requirements of the legislation on participation in the shared-equity construction of apartment buildings and (or) other real estate objects.
# 772004479216
Unscheduled inspection
Start date: 2020-08-07, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 771903371654
Unscheduled inspection
Start date: 2019-09-05, end date: 2019-10-02, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: the purpose and objective of this audit is to verify compliance with the mandatory requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects. The subject of an unscheduled documentary audit is compliance with the requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects
# 77180803185417
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-08-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803162711
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-07-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803158851
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803102558
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803059222
Unscheduled inspection
Start date: 2018-01-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803054889
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-01-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802762558
Unscheduled inspection
Start date: 2017-10-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802508950
Unscheduled inspection
Start date: 2017-09-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701726136
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-06-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701556247
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-05-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701297236
Unscheduled inspection
Start date: 2017-01-13, end date: 2017-01-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used