# 77180803185076
Unscheduled inspection
Start date: 2018-07-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803125730
Unscheduled inspection
Start date: 2018-04-19, end date: 2018-04-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 471801960514
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-28, duration: —
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Implementation of federal state supervision over the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms in connection with the receipt of information from the Social Insurance Fund Vh 622618PV