# 00160700999041
Unscheduled inspection
Start date: 2016-10-12, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162004475979
Unscheduled inspection
Start date: 2020-08-10, end date: 2020-08-21, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such works, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 12052020 case 190420190022 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 162004410116
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of the capital construction facility of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 12052020 case 190420190022 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts
# 161903702497
Unscheduled inspection
Start date: 2019-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903853847
Unscheduled inspection
Start date: 2019-10-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161903883441
Unscheduled inspection
Start date: 2019-10-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 161902913001
Unscheduled inspection
Start date: 2019-08-07, end date: 2019-08-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Opredelenie sootvetstviya vypolnennyh rabot primenennyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov proverka nalichiya razresheniya na stroitelstvo vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa RF v sootvetstvii s programmoi proverok ot 14022019 delo 151120180049 preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam proektnoi dokumentacii
# 161902838647
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-26, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 14062019 case 190420190022the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902838939
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the process of reconstruction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipment of capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 14062019 case 190420190022the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out reconstruction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this audit is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 161902774329
Unscheduled inspection
Start date: 2019-06-13, end date: 2019-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Opredelenie sootvetstviya vypolnennyh rabot primenennyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov proverka nalichiya razresheniya na stroitelstvo vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa RF v sootvetstvii s programmoi proverok ot 14022019 delo 151120180049 preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam proektnoi dokumentacii
# 161902660253
Unscheduled inspection
Start date: 2019-04-24, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161902442021
Unscheduled inspection
Start date: 2019-01-23, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 161802160466
Unscheduled inspection
Start date: 2018-12-04, end date: 2018-12-05, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction reconstruction of the capital construction facility of building materials and the results of such works with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of capital construction facilities with metering devices for energy resources used checking the availability of a construction permit compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation prevention as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation compliance with mandatory requirements or requirements established by municipal legal acts
# 161801938193
Unscheduled inspection
Start date: 2018-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701839991
Unscheduled inspection
Start date: 2017-07-20, end date: 2017-08-16, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: control over the execution of the prescription
# 16160701218981
Unscheduled inspection
Start date: 2016-12-09, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160701218177
Unscheduled inspection
Start date: 2016-12-09, end date: 2016-12-12, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya ustranennyh narushenii trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii drugih normativnyh aktov norm i pravil a takzhe s celyu sostavleniya akta ob ustranenii narushenii na osnovanii postupivshego v Inspekciyu izvescheniya ot 05122016 10949 ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva kotorye bylo predpisano ustranit v srok ustanovlennyi predpisaniem ot 30112016 1319066301 do 12122016gZadachami nastoyaschei proverki yavlyayutsyapreduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii vypolnenie predpisanii Inspekcii
# 16160701144628
Unscheduled inspection
Start date: 2016-11-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701058815
Unscheduled inspection
Start date: 2016-11-02, end date: 2016-11-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: The inspection is carried out in order to determine the compliance of the completed works and applied building materials during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used. The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer customer carrying out construction on the basis of a contract with the developer or the customer of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and design documentationthe subject of this audit is Compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations of other regulatory legal acts and project documentation
# 16160701135915
Unscheduled inspection
Start date: 2016-11-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160701131999
Unscheduled inspection
Start date: 2016-11-21, end date: 2016-11-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya vypolnennyh rabot primenyaemyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa RF v sootvetstvii s programmoi proverok ot 04082016 delo 121120160058Zadachami nastoyaschei proverki yavlyayutsyapreduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya vybrat nuzhnoe soblyudenie obyazatelnyh trebovanii
# 16160701139509
Unscheduled inspection
Start date: 2016-11-22, end date: 2016-11-30, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya fakta ispolneniya predpisaniya ot 14102016 1219101901 srok ispolneniya kotorogo istek 07112016 i sostavleniya akta po rezultatam proverkiZadachami nastoyaschei proverki yavlyayutsyapreduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii vypolnenie predpisanii Inspekcii
# 16160700996784
Unscheduled inspection
Start date: 2016-10-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700996735
Unscheduled inspection
Start date: 2016-10-13, end date: 2016-10-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya ustranennyh narushenii trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii drugih normativnyh aktov norm i pravil a takzhe s celyu sostavleniya akta ob ustranenii narushenii na osnovanii postupivshego v Inspekciyu izvescheniya ot 29092016 8567 ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva kotorye bylo predpisano ustranit v srok ustanovlennyi predpisaniem ot 15092016 1219088301 do 29092016gZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii pri ustranenii ranee vyyavlennyh narusheniiPredmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisanii Inspekcii
# 00160700999041
Unscheduled inspection
Start date: 2016-10-12, end date: 2016-10-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya vypolnyaemyh rabot primenyaemyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov na osnovanii postupivshego v Inspekciyu izvescheniya ot 03102016 8652 o srokah zaversheniya rabot kotorye podlezhat proverke na obekte kapitalnogo stroitelstvaZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii
# 16160700724857
Unscheduled inspection
Start date: 2016-09-22, end date: 2016-09-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentationcompliance with mandatory requirements or requirements established by municipal legal acts
# 16160700822745
Unscheduled inspection
Start date: 2016-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700598180
Unscheduled inspection
Start date: 2016-09-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16160700593519
Unscheduled inspection
Start date: 2016-09-15, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 16160700100138
Unscheduled inspection
Start date: 2016-08-31, end date: 2016-08-31, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya ustranennyh narushenii trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii drugih normativnyh aktov norm i pravil a takzhe s celyu sostavleniya akta ob ustranenii narushenii na osnovanii postupivshego v Inspekciyu izvescheniya ot 24082016 7244 ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva kotorye bylo predpisano ustranit v srok ustanovlennyi predpisaniem ot 17082016 1219072301 do 24082016gZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentacii pri ustranenii ranee vyyavlennyh narushenii6 Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya
# 16160601792567
Unscheduled inspection
Start date: 2016-08-17, end date: 2016-08-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu opredeleniya sootvetstviya vypolnennyh rabot primenennyh v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva stroitelnyh materialov rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obektov kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa RF v sootvetstvii s programmoi proverok ot 04082016 delo 121120160058Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie a takzhe vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii sootvetstviya vypolnyaemyh v processe stroitelstva obekta kapitalnogo stroitelstva rabot trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii ili trebovanii ustanovlennyh municipalnymi pravovymi aktami
# 16160601751136
Unscheduled inspection
Start date: 2016-08-18, end date: 2016-08-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works applied during the construction reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in in accordance with the inspection program from 20012016 case 193320130052, the tasks of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is the compliance of the information contained in the notification of the beginning implementation of certain types of entrepreneurial activity by mandatory requirements compliance with mandatory requirements or requirements established by municipal legal acts