Found 37 inspections:

# 001800014268
Unscheduled inspection
Start date: 2018-01-25, end date: 2018-02-02, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with Rostechnadzor Order No. 15032017 85 "On inspections of organizations operating tower cranes" based on the instruction of Deputy Prime Minister of the Russian Federation AG Khloponin dated 08022017 AHP9682 "On the organization and conduct of unscheduled inspections of organizations operating tower cranes from 2017 to 2019" The objectives of this inspection are to prevent, detect and suppress violations mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety and technical regulation of mandatory requirements taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts The subject of this audit is compliance by a legal entity in the course of its activities with mandatory requirements industrial safety in the design construction operation conservation and liquidation of hazardous production facilities manufacture installation commissioning maintenance and repair of technical devices for tower cranes used at hazardous production facilities compliance with the specified requirements of buildings, facilities, equipment and materials used, as well as requirements for machinery and equipment and related requirements for these products processes of operation and disposal


# 662101350208
Unscheduled inspection
Start date: 2021-11-22, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662101350200
Unscheduled inspection
Start date: 2021-11-22, end date: 2021-12-17, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to implement the inspection program No. 29-19-17/209-20 dated 08/17/2020 (Amendment No. 1), the task of this inspection is to carry out regional state construction supervision. The subject of this audit is: verification of the conformity of the work performed and the building materials used in the construction of the capital construction facility "Residential development of three nine-storey residential buildings with built-in non-residential premises at the address: Sverdlovsk region, Nizhny Tagil, Vagonostroiteley Avenue, 39. Stage 2 - residential building No. 2", located at: Sverdlovskaya Nizhny Tagil region, 39 Vagonostroiteley Ave., as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a building permit; compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 662101238632
Unscheduled inspection
Start date: 2021-10-25, end date: 2021-11-23, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out on the basis of a notice of completion of the construction of a capital construction facility. No. 29-19-41/46008 dated 18.10.2021, in accordance with the inspection program dated 05.07.2021 No. 29-19-24/109-17, the task of this inspection is to carry out regional state construction supervision. The subject of this audit is: verification of the conformity of the work performed and the building materials used during the construction of the capital construction facility "Residential development of four nine-storey buildings with integrated office space at the address: Sverdlovsk region, Nizhny Tagil, Chernoistochinskoe highway, building No. 17. Residential building No. 3", located at: Sverdlovsk region, Nizhny Tagil, Chernoistochinskoe Highway, Building No. 17, as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for used energy resources; availability of building permits; meeting the requirements set out in Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 662100638685
Unscheduled inspection
Start date: 2021-09-09, end date: 2021-09-20, duration: 8
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to control the execution of a previously issued instruction on the elimination of identified violations; Tasks - the implementation of regional state construction supervision; Subject - the implementation of a previously issued instruction on the elimination of an identified violation of mandatory requirements


# 662100446095
Unscheduled inspection
Start date: 2021-08-16, end date: —, duration:
Authority:
Purpose of inspection:


# 662100338469
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration:
Authority:
Purpose of inspection:


# 662100328016
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662100263013
Unscheduled inspection
Start date: 2021-06-08, end date: 2021-07-06, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program No. 29-19-17/209-20 dated 2020-08-17; The tasks are to carry out regional state construction supervision; The subject is to verify the conformity of work performed and applicable building materials during the construction of a capital construction facility: Residential development of three nine-storey residential buildings with built-in non-residential premises at the address: Sverdlovsk region, Nizhny Tagil, Prospekt Vagonostroiteley, 39. Stage 2 - residential building No. 2, located at: Sverdlovsk region, Nizhny Tagil, Prospekt Vagonostroiteley, 39, the results of such work requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation of the project documentation, including the requirements for energy efficiency (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used; the availability of a construction permit; meeting the requirements set out in parts 2, 3 and 3.1 of Articles 52 of the Urban Planning Code of the Russian Federation.


# 662100151687
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-05-18, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program No. 29-19-17/209-20 dated 2020-08-13; The tasks are to carry out regional state construction supervision; The subject is to verify the conformity of work performed and applicable building materials during the construction of a capital construction facility: Residential development of three nine-storey residential buildings with built-in non-residential premises at the address: Sverdlovsk region, Nizhny Tagil, Prospekt Vagonostroiteley, 39. Stage 2 - residential building No. 2, located at: Sverdlovsk region, Nizhny Tagil, Prospekt Vagonostroiteley, 39, the results of such work requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation of the project documentation, including the requirements for energy efficiency (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; meeting the requirements set out in parts 2, 3 and 3.1 of Articles 52 of the Urban Planning Code of the Russian Federation.


# 662105327618
Unscheduled inspection
Start date: 2021-02-01, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662005236431
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the audit is to implement the inspection program 29191720920 dated 17082020. The purpose of this audit is to carry out regional state construction supervision. The subject of this audit is to verify the compliance of work performed and building materials used during the construction of the capital construction facility "Residential buildings consisting of three nine-storey residential buildings with built-in non-residential premises at 39 Vagonostroiteley Avenue, Nizhny Tagil, Sverdlovsk region, stage 2 residential house 2" located at 39 Vagonostroiteley Ave., Nizhny Tagil, Sverdlovsk Region, as well as the results of such work to the requirements of project documentation specified in paragraph 1 of Part 5 of Article 49 of the Urban Planning Code of the Russian Federation, including project documentation that takes into account changes made in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including energy requirements efficiency and requirements for equipping the capital construction facility with metering devices for used energy resources


# 662005236547
Unscheduled inspection
Start date: 2020-11-25, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662004478801
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-09-11, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29190116019 dated 300-52019 Tasks implementation of regional state construction supervision The subject is to verify the compliance of work and applicable building materials during the construction of a capital construction facility Residential buildings consisting of three nine-storey residential buildings with built-in non-residential premises at 39 Vagonostroiteley Avenue, Sverdlovsk region Nizhny Tagil 9-storey residential buildings 1 2 3 with built-in non-residential premises 1 stage 1 residential building block transformer substation 2 of the BCTP located at the address Nizhny Tagil railway station, Sverdlovsk region, 39 of the results of such work meet the requirements of the design documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects that are not subject to energy efficiency requirements and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 662004400448
Unscheduled inspection
Start date: 2020-04-27, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662004367180
Unscheduled inspection
Start date: 2020-03-23, end date: —, duration:
Authority:
Purpose of inspection:


# 662004367194
Unscheduled inspection
Start date: 2020-03-23, end date: —, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection:


# 662004196888
Unscheduled inspection
Start date: 2020-01-20, end date: —, duration:
Authority:
Purpose of inspection:


# 661903594335
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-10-18, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the audit is to implement the inspection program dated 300-52019 29190116019. The objectives of this audit are to carry out regional state construction supervision. The purpose of this audit is to verify the compliance of work performed and building materials used during the construction of the capital construction facility "Residential buildings consisting of three nine-storey residential buildings with built-in non-residential premises at 39 Vagonostroiteley Avenue, Nizhny Tagil, Sverdlovsk region, 9-storey residential buildings 1 2 3 with built-in non-residential premises 1 stage residential building 1 block transformer substation 2 BKTP" located at 39 Vagonostroiteley Avenue, Nizhny Tagil, Sverdlovsk region, as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities that do not meet energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used. building permits comply with the requirements set out in Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661903205034
Unscheduled inspection
Start date: 2019-09-06, end date: —, duration:
Authority:
Purpose of inspection:


# 661902994938
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-20, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: the purpose of the inspection program dated April 10, 2018 29190111818 the task is to carry out regional state construction supervision the subject is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Integrated residential development at the address Sverdlovsk region Nizhny Tagil Uralsky Prospekt stage 2 9-storey residential buildings 123 with built-in offices 9-storey residential building 1 with built-in offices" located at the address Sverdlovsk region, Nizhny Tagil city, Uralsky Prospekt, the results of such work meet the requirements of the design documentation, including energy efficiency requirements


# 661902918177
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-30, duration: 20
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose is to implement the inspection program dated December 07, 2018 291901394163 the task is to carry out regional state construction supervision the subject of the CST is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction stage 2 9-storey residential building 2 with built-in office space" located at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway Stroitelny 17 the results of such work meet the requirements of project documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of permits for construction and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661902439959
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-02-15, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: objectives implementation of the inspection program dated December 06, 2018 291901394163 tasks implementation of the regional State construction supervision Committee's proposal to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction stage 2 9-storey residential building construction 2 with built-in office premises" located at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway Stroitelny 17 the results of such work meet the requirements of project documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and meeting the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661801593677
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration:
Authority:
Purpose of inspection:


# 661801593661
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-10-19, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: In order to implement the inspection program 29190110917 dated April 18, 2018, the objectives of this audit are to carry out regional state construction supervision. 7 The subject of this audit is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe Highway construction 17 Stage 4 Residential Building 3" located at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe Highway Stroitelny 17 the results of such work meet the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federations


# 661800626518
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-09-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29190110917 dated April 18, 2018, the purpose of this inspection is to carry out regional state construction supervision. The subject is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction stage 4 Residential building 3" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk Region, the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800626613
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-09-07, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29190110817 dated March 20, 2018, the purpose of this inspection is to carry out regional state construction supervision. The subject is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction stage 4 Residential building 4" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk Region, the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800515450
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-08-01, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The OBJECTIVES of the inspection program dated November 30, 2017 29190139416 2 TASKS implementation of state construction supervision The subject of the CST is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction stage 2 9-storey residential house of construction 2 with built-in office premises" located at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway stroitelny 17 results of such work to building codes and rules sanitary and epidemiological rules and regulations safety rules and state standards as well as the requirements of other regulatory legal acts of the Russian Federation and regulatory legal acts of federal executive authorities subject to mandatory execution during the construction of capital construction, as well as the availability of a building permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800319708
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29190110917 dated April 18, 2018, the objectives of this audit are to carry out regional state construction supervision. 7 The subject of this audit is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway building 17 Stage 4 Residential Building 3" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk region, results of such work to the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 661800319532
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-11, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the inspection program 29190110817 dated March 20, 2018, the objectives of this audit are to carry out regional state construction supervision. 7 The subject of this audit is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway building 17 Stage 4 Residential building 4" located at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway Stroitelny 17 the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 001800014268
Unscheduled inspection
Start date: 2018-01-25, end date: 2018-02-02, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with Rostechnadzor Order No. 15032017 85 "On inspections of organizations operating tower cranes" based on the instruction of Deputy Prime Minister of the Russian Federation AG Khloponin dated 08022017 AHP9682 "On the organization and conduct of unscheduled inspections of organizations operating tower cranes from 2017 to 2019" The objectives of this inspection are to prevent, detect and suppress violations mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety and technical regulation of mandatory requirements taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have committed violations of the requirements of federal laws and other regulatory legal acts The subject of this audit is compliance by a legal entity in the course of its activities with mandatory requirements industrial safety in the design construction operation conservation and liquidation of hazardous production facilities manufacture installation commissioning maintenance and repair of technical devices for tower cranes used at hazardous production facilities compliance with the specified requirements of buildings, facilities, equipment and materials used, as well as requirements for machinery and equipment and related requirements for these products processes of operation and disposal


# 66170802727863
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-27, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: in order to monitor the implementation of the previously issued regulation on the elimination of identified violations of mandatory requirements 291905160 dated July 11, 2017, the objectives of this audit are to carry out regional state construction supervision 7The purpose of this audit is to comply with the previously issued regulation on the elimination of identified violations of mandatory requirements 291905160 dated July 11, 2017


# 66170802727832
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: in order to implement the inspection program 29190110917 dated April 27, 2017, the objectives of this audit are to carry out regional state construction supervision 7The purpose of this audit is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction Stage 4 Residential Building 3" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk region, results of such work to the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 66170802727894
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: in order to implement the inspection program 29190110817 dated April 27, 2017, the objectives of this audit are to carry out regional state construction supervision 7The purpose of this audit is to verify the compliance of work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway 17 construction Stage 4 Residential Building 4" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk region, results of such work to the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 66170701719231
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-07-14, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: It is carried out in order to implement the inspection program 29190110917 dated April 27, 2017. The objectives of this inspection are to carry out regional state construction supervision. The purpose of this inspection is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with built-in office premises at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway building 17 Stage 4 Residential Building 3" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk region, results of such work to the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 66170701719200
Unscheduled inspection
Start date: 2017-06-20, end date: 2017-07-14, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: In order to implement the inspection program 29190110817 dated April 27, 2017, the objectives of this audit are to carry out regional state construction supervision. The subject of this audit is to verify the compliance of the work and applicable building materials during the construction of the capital construction facility "Residential buildings of four nine-storey buildings with integrated office space at the address Sverdlovsk region Nizhny Tagil Chernoistochinskoe highway building 17 Stage 4 Residential Building 4" located at 17 Chernoistochinskoe Highway, Nizhny Tagil, Sverdlovsk region, results of such work to the requirements of the technical regulations of the project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code Of the Russian Federation


# 66170701304176
Unscheduled inspection
Start date: 2017-01-19, end date: 2017-01-23, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this audit is being conducted in order to monitor the implementation of the previously issued instruction on the elimination of identified violations of mandatory requirements 291904365 dated November 28, 2016The purpose of this audit is to comply with the previously issued instruction on the elimination of identified violations of mandatory requirements 291904365 dated November 28, 2016The task of this audit is to carry out state construction supervision


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.