Found 7 inspections:

# 242100297138
Unscheduled inspection
Start date: 2021-06-23, end date: —, duration:
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 242100101874
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu proverki vypolneniya meropriyatii, predusmotrennyh punktami ranee vydannogo proveryaemomu licu predpisaniya ot 11.11.2020 № 09/413/1-S ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii, srok ispolneniya kotorogo istek. Zadachei nastoyaschei proverki yavlyaetsya ustanovlenie fakta ustraneniya ranee vyyavlennyh narushenii predpisaniya ot 11.11.2020 № 09/413/1-S, v ustanovlennyi srok. Predmetom nastoyaschei proverki, yavlyaetsya proverka vypolneniya predpisaniya organa gosudarstvennogo stroitelnogo nadzora ot 11.11.2020 № 09/413/1-S


# 242100101838
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu proverki vypolneniya meropriyatii, predusmotrennyh punktami ranee vydannogo proveryaemomu licu predpisaniya ot 11.11.2020 № 09/412/1-S ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii, srok ispolneniya kotorogo istek. Zadachei nastoyaschei proverki yavlyaetsya ustanovlenie fakta ustraneniya ranee vyyavlennyh narushenii predpisaniya ot 11.11.2020 № 09/412/1-S, v ustanovlennyi srok. Predmetom nastoyaschei proverki, yavlyaetsya proverka vypolneniya predpisaniya organa gosudarstvennogo stroitelnogo nadzora ot 11.11.2020 № 09/412/1-S


# 242100092551
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-23, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora pri stroitelstve ukazannogo obekta kapitalnogo stroitelstva, v svyazi s nastupleniem srokov zaversheniya rabot, kotorye podlezhat proverke v sootvetstvii s utverzhdennoi programmoi provedeniya proverok pri stroitelstve obekta kapitalnogo stroitelstva. Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie i presechenie narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, trebovanii proektnoi dokumentacii. Predmetom nastoyaschei proverki, yavlyaetsya: Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; Proverka nalichiya razresheniya na stroitelstvo; Proverka vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 242100092535
Unscheduled inspection
Start date: 2021-03-29, end date: 2021-04-23, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora pri stroitelstve ukazannogo obekta kapitalnogo stroitelstva, v svyazi s nastupleniem srokov zaversheniya rabot, kotorye podlezhat proverke v sootvetstvii s utverzhdennoi programmoi provedeniya proverok pri stroitelstve obekta kapitalnogo stroitelstva. Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie i presechenie narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, trebovanii proektnoi dokumentacii. Predmetom nastoyaschei proverki, yavlyaetsya: Proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; Proverka nalichiya razresheniya na stroitelstvo; Proverka vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 002005221196
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-11, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to carry out state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates that are subject to verification in accordance with the approved program of inspections during the construction of a capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development and project documentationthe subject of this inspection is to verify compliance with the implementation of works and construction materials used during the construction of a capital construction facility, as well as the results of such work, to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, Verification of the availability of a construction permit, verification of compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190 FZ


# 002005221166
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-12-11, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to carry out state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates that are subject to verification in accordance with the approved program of inspections during the construction of a capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development and project documentationthe subject of this inspection is to verify compliance with the implementation of works and construction materials used during the construction of a capital construction facility, as well as the results of such work, to the requirements of design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, Verification of the availability of a construction permit, verification of compliance with the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation dated 29122004 190 FZ


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.