# 77180803124947
Unscheduled inspection
Start date: 2018-04-13, end date: 2018-04-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803108024
Unscheduled inspection
Start date: 2018-03-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803087303
Unscheduled inspection
Start date: 2018-02-09, end date: 2018-02-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803081304
Unscheduled inspection
Start date: 2018-01-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803064392
Unscheduled inspection
Start date: 2018-01-16, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803068274
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802902361
Unscheduled inspection
Start date: 2017-11-30, end date: 2017-12-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802788685
Unscheduled inspection
Start date: 2017-10-27, end date: 2017-11-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802743298
Unscheduled inspection
Start date: 2017-10-17, end date: 2017-10-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802788068
Unscheduled inspection
Start date: 2017-10-31, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170802573507
Unscheduled inspection
Start date: 2017-09-25, end date: 2017-09-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170801934550
Unscheduled inspection
Start date: 2017-09-01, end date: 2017-09-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701864822
Unscheduled inspection
Start date: 2017-08-09, end date: 2017-08-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701738486
Unscheduled inspection
Start date: 2017-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701667761
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used