Found 3 inspections:

# 002004236280
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-01-27, duration:
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the fulfillment by the limited liability company "Modern Heat Supply Technologies" of the previously issued instruction dated 30082019 610594vnP0064K2019, hereinafter referred to as the Instruction, the deadline for which has expired. The purpose of this inspection is to establish the facts of non-fulfillment by the limited liability company "Modern Heat Supply Technologies" of the Instruction


# 002004236280
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-01-27, duration:
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the fulfillment by the limited liability company "Modern Heat Supply Technologies" of the previously issued instruction dated 30082019 610594vnP0064K2019, hereinafter referred to as the Instruction, the deadline for which has expired. The purpose of this inspection is to establish the facts of non-fulfillment by the limited liability company "Modern Heat Supply Technologies" of the Instruction


# 001902980360
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-08-30, duration:
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the progress of preparation of heat supply facilities for operation in the autumn winter period of 2019-2020 on the basis of the instruction of the Government of the Russian Federation dated 19062019 VMP95084 and the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 "On monitoring the progress of preparation of heat supply facilities for operation in the autumn winter period of 2019-2020"The purpose of this audit is to monitor the progress of the preparation of heat supply facilities for operation in the autumn winter period of 2019-2020. The subject of this audit is compliance by a legal entity with mandatory requirements for the operation of thermal power plants and heating networks and their maintenance in good condition aimed at ensuring reliable heat supply while preparing enterprises for the upcoming autumn winter period


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.