Found 7 inspections:

# 432100077613
Unscheduled inspection
Start date: 2021-03-15, end date: —, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Kirovskoi oblasti
Purpose of inspection: control over the implementation of regulation No. 57/1/1 dated 02/28/2019 on the elimination of violations of fire safety requirements, the deadline for which expired on 03/01/2020.


# 432004340022
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Kirovskoi oblasti
Purpose of inspection: control over the implementation of paragraphs 13 7 8 1363 of regulation 5711 of 28022019 on the elimination of violations of fire safety requirements, the deadline for which expires on 01032020


# 431903642006
Unscheduled inspection
Start date: 2019-09-20, end date: 2019-10-16, duration:
Authority: Gosudarstvennaya inspekciya truda v Kirovskoi oblasti
Purpose of inspection: implementation of state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms on the basis of information received by the State Labor Inspectorate in the Kirov region on the fact of harm to the life and health of a citizen


# 431802312465
Unscheduled inspection
Start date: 2018-12-24, end date: 2019-01-10, duration:
Authority: Ministerstvo stroitelstva Kirovskoi oblasti
Purpose of inspection: Objectives Verification of the completed capital construction facility tasks Prevention identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, Subject to compliance with mandatory requirements or requirements established by municipal legal acts


# 43170802805541
Unscheduled inspection
Start date: 2017-10-18, end date: 2017-10-23, duration:
Authority: Gosudarstvennaya inspekciya truda v Kirovskoi oblasti
Purpose of inspection: Enforcement of labor protection legislation


# 43170802612752
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-03, duration:
Authority: Ministerstvo stroitelstva Kirovskoi oblasti
Purpose of inspection: Objectives Implementation of the verification task program Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentationsubject Compliance with mandatory requirements or requirements established by municipal legal acts committed by the developer, the customer and the person carrying out construction on the basis of an agreement with the developer or the customer


# 43170701482714
Unscheduled inspection
Start date: 2017-03-29, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.