Found 20 inspections:

# 001903415742
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration:
Authority:
Purpose of inspection:


# 00160700691160
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-10-21, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment of paragraphs 130 of the regulation dated 26082016 576073P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Limited Liability Company "Teplomontazhnaladka"The subject of this audit is to note the necessary compliance with the instructions of the state control bodies supervision of municipal control bodies


# 00160700085184
Unscheduled inspection
Start date: 2016-09-12, end date: —, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00160601717203
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the progress of preparation of electric and heat supply organizations for work in the autumn-winter period of 2016-2017. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The purpose of this audit is to ensure compliance with mandatory requirements or requirements established by legal acts


# 00150601351298
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-12-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 23092015 575379P issued by the North Ural Department of Rostechnadzor


# 00150601351273
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-11-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 09092015 574790P1 issued by the North Ural Department of Rostechnadzor


# 00150601351266
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-12-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 09092015 574790P2 issued by the North Ural Department of Rostechnadzor


# 00150600161574
Unscheduled inspection
Start date: 2015-09-10, end date: 2015-09-24, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the order from 04022015 g 5710959P issued by the North Ural Department of Rostechnadzor


# 00150600027715
Unscheduled inspection
Start date: 2015-08-20, end date: 2015-09-09, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric and heat supply organizations for work in the autumn-winter period 20152016


# 722004237654
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-02-19, duration: 20
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: Implementation of regional state housing supervision on the basis of consideration of an application from 10012020 0066j20 for an apartment building Tobolsk rn d Bashkova Dorozhnikov str. 2a compliance with mandatory requirements for determining the amount and payment of utility bills compliance with mandatory requirements


# 001903415742
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-11, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this audit is carried out in order to verify compliance with the regulation dated August 6, 2019 G574768 The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts in the field of energy security and take measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of federal laws and other regulatory legal acts by the subject of this audit is the fulfillment of the mandate of the state control authority supervision of the municipal control authority


# 001902873333
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-08-06, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the progress of the preparation of electric power facilities for operation in the autumn-winter period 2019-2020. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is compliance with mandatory requirements or requirements established by legal acts


# 00160700691160
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-10-21, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment of paragraphs 130 of the regulation dated 26082016 576073P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Limited Liability Company "Teplomontazhnaladka"The subject of this audit is to note the necessary compliance with the instructions of the state control bodies supervision of municipal control bodies


# 00160700085184
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-10-07, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment of paragraphs 117 of the regulation dated 23122015 g 577821P issued by the North Ural Department of Rostechnadzor The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Limited Liability Company "Teplomontazhnaladka" The subject of this audit is to note the necessary compliance with the instructions of state control bodies supervision of municipal control bodies


# 00160601717203
Unscheduled inspection
Start date: 2016-08-01, end date: 2016-08-26, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the progress of preparation of electric and heat supply organizations for work in the autumn-winter period of 2016-2017. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The purpose of this audit is to ensure compliance with mandatory requirements or requirements established by legal acts


# 00150601351298
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-12-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 23092015 575379P issued by the North Ural Department of Rostechnadzor


# 00150601351273
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-11-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 09092015 574790P1 issued by the North Ural Department of Rostechnadzor


# 00150601351266
Unscheduled inspection
Start date: 2015-12-10, end date: 2015-12-23, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 09092015 574790P2 issued by the North Ural Department of Rostechnadzor


# 00150600161574
Unscheduled inspection
Start date: 2015-09-10, end date: 2015-09-24, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the order from 04022015 g 5710959P issued by the North Ural Department of Rostechnadzor


# 00150600027715
Unscheduled inspection
Start date: 2015-08-20, end date: 2015-09-09, duration:
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric and heat supply organizations for work in the autumn-winter period 20152016


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.