Found 20 inspections:

# 741802153186
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-07, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation for the installation of sections of a low-pressure gas pipeline the development of a trench the installation of a foundation welding insulation of joints laying of a pipeline backfilling after completion of work and the construction materials used during the construction of a capital construction facility as well as the results of such work


# 741802031072
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-12, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work with the installation of sections of a low-pressure gas pipeline the development of a trench the installation of a foundation welding insulation of joints laying of a pipeline backfilling during the work Installation of a GRP and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code Russian Federation


# 741801879812
Unscheduled inspection
Start date: 2018-10-08, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 741800783223
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-14, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work installation of sections of a low-pressure gas pipeline development of a trench foundation installation welding insulation of joints laying of a pipeline backfilling during work and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800674490
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-07, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot montazh uchastkov gazoprovoda nizkogo davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka v processe rabot Montazh nadzemnyh uchastkov gazoprovoda nizkogo davleniya burenie yam pod opory ustroistvo betonnyh fundamentov opor ustanovka opor montazh pokraska v processe rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741801460712
Unscheduled inspection
Start date: 2018-09-27, end date: 2018-10-03, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot ustroistvo naruzhnyh setei gazosnabzheniya posle zaversheniya rabot ustroistvo vnutrennih sistem gazosnabzheniya otopleniya posle zaversheniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800605301
Unscheduled inspection
Start date: 2018-08-14, end date: 2018-08-20, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work installation of sections of a low-pressure gas pipeline development of a trench foundation installation welding insulation of joints laying of a pipeline backfilling during work and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800605746
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-08-31, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot razbivka trassy gazoprovoda montazh uchastkov gazoprovoda nizkogo davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka v processe rabot Montazh nadzemnyh uchastkov gazoprovoda nizkogo davleniya burenie yam pod opory ustroistvo betonnyh fundamentov opor ustanovka opor montazh pokraska v processe rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800493105
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration:
Authority:
Purpose of inspection:


# 741800471717
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-06-29, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Sootvetstvie vypolneniya rabot ustroistvo naruzhnyh setei gazosnabzheniya v processe rabot ustroistvo vnutrennih sistem gazosnabzheniya otopleniya v processe rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii 2 Nalichie razresheniya na stroitelstvo 3 Vypolnenie trebovanii chch 23 i 31 st52 Gradostroitelnogo kodeksa RF


# 741800412271
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-08, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work installation of sections of a low-pressure gas pipeline development of a trench foundation installation welding insulation of joints laying of a pipeline backfilling during work and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800310287
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-07, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work installation of sections of a low-pressure gas pipeline development of a trench foundation installation welding insulation of joints laying of a pipeline backfilling during work and the construction materials used during the construction of a capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800231800
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-06, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Conformity of work execution breakdown of the gas pipeline route installation of high and medium pressure gas pipeline sections development of the trench foundation device welding insulation of joints laying of the pipeline backfilling after completion of work Installation of low pressure gas pipeline sections development of the trench foundation device welding insulation of joints laying of the pipeline backfilling during work and the construction materials used during the construction of the capital construction facility as well as the results of such works to the requirements of the technical regulations of the project documentation 2 The availability of a building permit 3 The fulfillment of the requirements of hh 23 and 31 ct52 of the Urban Planning Code of the Russian Federation


# 74170701676548
Unscheduled inspection
Start date: 2017-06-14, end date: —, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:


# 74170701596469
Unscheduled inspection
Start date: 2017-05-16, end date: 2017-05-19, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot zemlyanye raboty na gazoprovode srednego davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka posle zaversheniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF


# 74170701528673
Unscheduled inspection
Start date: 2017-04-17, end date: —, duration:
Authority:
Purpose of inspection:


# 74170701449506
Unscheduled inspection
Start date: 2017-03-20, end date: 2017-03-24, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot zemlyanye raboty na gazoprovode vysokogo davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka v processe rabot Montazh nadzemnyh uchastkov gazoprovoda vysokogo davleniya burenie yam pod opory ustroistvo betonnyh fundamentov opor ustanovka opor montazh pokraska v processe rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF


# 74170701310212
Unscheduled inspection
Start date: 2017-01-25, end date: 2017-01-27, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot zemlyanye raboty na gazoprovode vysokogo davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka posle zaversheniya rabot Montazh nadzemnyh uchastkov gazoprovoda vysokogo davleniya burenie yam pod opory ustroistvo betonnyh fundamentov opor ustanovka opor montazh pokraska posle zaversheniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF


# 74160701226285
Unscheduled inspection
Start date: 2016-12-21, end date: 2016-12-22, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1Sootvetstvie vypolneniya rabot zemlyanye raboty na gazoprovode vysokogo davleniya razrabotka transhei ustroistvo osnovaniya svarka izolyaciya stykov ukladka truboprovoda obratnaya zasypka v processe rabot Montazh nadzemnyh uchastkov gazoprovoda vysokogo davleniya burenie yam pod opory ustroistvo betonnyh fundamentov opor ustanovka opor montazh pokraska v processe rabot Ustanovka GRPSH i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii2Nalichie razresheniya na stroitelstvo3Vypolnenie trebovanii chch 23 st52 Gradostroitelnogo kodeksa RF


# 74160700915884
Unscheduled inspection
Start date: 2016-10-11, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.