# 632101452392
Unscheduled inspection
Start date: 2021-12-15, end date: —, duration: 2
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 632101388406
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 632101325167
Unscheduled inspection
Start date: 2021-11-15, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.
# 631902907390
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-09, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631902807525
Unscheduled inspection
Start date: 2019-06-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631902682778
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-05-08, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used