# 77190803447373
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-02, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: carrying out control measures in connection with the verification of the fulfillment of the instruction prevention detection and suppression of violations of the requirements of the design documentation of the legislation on urban development activities by the audited person verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 77190803431390
Unscheduled inspection
Start date: 2019-06-06, end date: 2019-06-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: provedenie meropriyatii po kontrolyu v svyazi s postupleniem izvescheniya zastroischika zakazchika preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnosti proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom
# 77190803412075
Unscheduled inspection
Start date: 2019-05-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803376897
Unscheduled inspection
Start date: 2019-03-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803322406
Unscheduled inspection
Start date: 2019-01-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802954502
Unscheduled inspection
Start date: 2017-12-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701702011
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160701060538
Unscheduled inspection
Start date: 2016-10-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160700856204
Unscheduled inspection
Start date: 2016-09-23, end date: 2016-10-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used
# 77160601718710
Unscheduled inspection
Start date: 2016-08-12, end date: 2016-08-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the inspection is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of a notification received from the developer, the customer or the person carrying out the construction on the commencement of work for which state construction supervision is provided. The objectives of this inspection are to prevent identify and suppress violations of technical regulations and design documentation committed by the audited person. The subject of this inspection is the compliance of the work and the applied construction materials in the process of construction reconstruction of the capital construction facility as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used