# 77180803176996
Unscheduled inspection
Start date: 2018-07-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170803018184
Unscheduled inspection
Start date: 2017-12-22, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170803008374
Unscheduled inspection
Start date: 2017-12-15, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802770060
Unscheduled inspection
Start date: 2017-10-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170801979105
Unscheduled inspection
Start date: 2017-09-19, end date: 2017-09-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170801966807
Unscheduled inspection
Start date: 2017-09-01, end date: 2017-09-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701873674
Unscheduled inspection
Start date: 2017-08-09, end date: 2017-08-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170801930275
Unscheduled inspection
Start date: 2017-08-23, end date: 2017-08-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701812074
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701708346
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701703861
Unscheduled inspection
Start date: 2017-06-13, end date: 2017-06-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701768640
Unscheduled inspection
Start date: 2017-06-30, end date: 2017-07-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701753325
Unscheduled inspection
Start date: 2017-06-27, end date: 2017-06-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701607966
Unscheduled inspection
Start date: 2017-05-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701585135
Unscheduled inspection
Start date: 2017-04-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701547110
Unscheduled inspection
Start date: 2017-04-21, end date: 2017-04-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701485841
Unscheduled inspection
Start date: 2017-03-28, end date: 2017-04-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701370397
Unscheduled inspection
Start date: 2017-02-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701302331
Unscheduled inspection
Start date: 2017-01-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701253390
Unscheduled inspection
Start date: 2016-12-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701101972
Unscheduled inspection
Start date: 2016-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701102889
Unscheduled inspection
Start date: 2016-11-11, end date: 2016-11-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used
# 77160700061271
Unscheduled inspection
Start date: 2016-08-26, end date: —, duration: —
Authority: —
Purpose of inspection: