# 772101369328
Unscheduled inspection
Start date: 2021-11-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100701518
Unscheduled inspection
Start date: 2021-09-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100341378
Unscheduled inspection
Start date: 2021-07-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100237325
Unscheduled inspection
Start date: 2021-05-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100033363
Unscheduled inspection
Start date: 2021-03-10, end date: 2021-03-25, duration: 12
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the inspection program; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: checking the elimination of violations specified in the instruction issued by Mosgosstroynadzor compliance of the work and the construction materials used in the construction, reconstruction process the capital construction facility, as well as the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772005273296
Unscheduled inspection
Start date: 2020-12-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004461919
Unscheduled inspection
Start date: 2020-07-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004225094
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771904058329
Unscheduled inspection
Start date: 2019-12-06, end date: 2019-12-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771903620962
Unscheduled inspection
Start date: 2019-09-24, end date: 2019-10-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit is to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including the requirements of energy efficiency and requirements for the equipment of the capital construction facility with metering devices for the energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803487410
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803456445
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803436654
Unscheduled inspection
Start date: 2019-06-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803415150
Unscheduled inspection
Start date: 2019-05-16, end date: 2019-05-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803361407
Unscheduled inspection
Start date: 2019-03-12, end date: 2019-03-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the capital construction facility with the requirements of technical regulations and design documentationthe prevention of detection and suppression of violations of technical regulations and design documentationthe compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices used energy resources
# 77190803327337
Unscheduled inspection
Start date: 2019-02-08, end date: 2019-03-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used