Found 122 inspections:

# 242004464964
Unscheduled inspection
Start date: 2020-07-20, end date: 2020-08-14, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 103 dated 17072020 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including project documentation7 The subject of this inspection is71 Verification of the conformity of the work performed and the construction materials used materials during the construction of a capital construction facility as well as the results of such work meet the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the information model They are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, all acts prescriptions notices on the elimination of violations and deficiencies identified during the implementation of regional state construction supervision72 Compliance with the requirements set out in Parts 2 are subject to verification. 3 and 31 of Articles 52 of the Urban Planning Code of the Russian Federation73 Verification of a building permit


# 242004464988
Unscheduled inspection
Start date: 2020-07-20, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 242004437919
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-07-17, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 73 dated 16062020 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including project documentation7 The subject of this inspection is71 Checking the compliance of the work and the applied construction materials during the construction of a capital construction facility, as well as the results of such work, meet the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the information model They are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, all acts prescriptions notices on the elimination of violations and deficiencies identified during the implementation of regional state construction supervision72 Compliance with the requirements set out in Parts 2 are subject to verification. 3 and 31 of Articles 52 of the Urban Planning Code of the Russian Federation73 Verification of a building permit


# 242004437584
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-07-17, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 74 dated 16062020 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including project documentation7 The subject of this inspection is71 Checking the compliance of the work and the applied construction materials during the construction of a capital construction facility as well as the results of such work meet the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the information model They are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, all acts prescriptions notices on the elimination of violations and deficiencies identified during the implementation of regional state construction supervision72 Compliance with the requirements set out in Parts 2 are subject to verification. Articles 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation73 Verification of a building permit


# 242004350887
Unscheduled inspection
Start date: 2020-03-17, end date: 2020-04-13, duration: 20
Authority: Departament gorodskogo hozyaistva administracii goroda Krasnoyarska
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of a previously issued instruction on the elimination of identified violations of the legislation on highways and the maintenance of the technical condition of highways in accordance with the requirements for an operational condition acceptable under the conditions of road safety, namely the prescription from 17022020 2gh, the deadline for which expires 160320the tasks of this inspection are to establish the fact of elimination of previously identified violations, to verify the actual The purpose of this inspection is to comply with the requirements of the order of the body exercising municipal control.


# 242004255354
Unscheduled inspection
Start date: 2020-02-12, end date: 2020-03-12, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: In order to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects, based on the results of a preliminary check on the failure to eliminate violations specified in the regulation dated 17102019 304DS within the prescribed time, motivated submission dated 280120208the tasks of this audit are to establish the elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed time The purpose of this audit is to comply with the requirements of the state control and supervision authorities.


# 242004191684
Unscheduled inspection
Start date: 2020-01-21, end date: 2020-02-17, duration: 20
Authority: Departament gorodskogo hozyaistva administracii goroda Krasnoyarska
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of a previously issued instruction on the elimination of identified violations of the legislation on highways and the maintenance of the technical condition of highways in accordance with the requirements for an operational condition acceptable under the conditions of road safety, namely the regulations from 07112019 532gh, the deadline for which expires 20012020the objectives of this inspection are to establish the fact of elimination of previously identified violations, to verify the actual The purpose of this inspection is to comply with the requirements of the order of the body exercising municipal control. The purpose of this inspection is to comply with the requirements of the order of the body exercising municipal control.


# 241903839787
Unscheduled inspection
Start date: 2019-10-22, end date: —, duration:
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Krasnoyarskomu krayu
Purpose of inspection:


# 241903806902
Unscheduled inspection
Start date: 2019-10-04, end date: 2019-10-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: In order to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects, based on the results of a preliminary check on the failure to eliminate violations specified in the regulation dated 22052019 102DS within the established time frame motivated submission dated 01102019 296, the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the established time frame. The deadline for the subject of this audit is the fulfillment of the instructions of the state control and supervision bodies


# 241903630971
Unscheduled inspection
Start date: 2019-09-18, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803437322
Unscheduled inspection
Start date: 2019-06-18, end date: 2019-07-01, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the previously issued to the person being checked Regulation No. 942SENiEK dated 26042019 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 17062019. The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the time period established by the regulation. The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision


# 241902788856
Unscheduled inspection
Start date: 2019-06-25, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803417393
Unscheduled inspection
Start date: 2019-05-24, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241902681390
Unscheduled inspection
Start date: 2019-04-22, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803377932
Unscheduled inspection
Start date: 2019-04-01, end date: —, duration:
Authority:
Purpose of inspection:


# 24190803362180
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-22, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose of the audit is to verify the fulfillment of the previously issued to the person being checked regulation 5283OZHS dated 25.012019 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 07032019 The objectives of the audit are to establish the fact of elimination of previously identified violations, to verify the actual work performed in accordance with the prescribed measures within the time period prescribed by the regulation The subject of the audit is to comply with the lawful order of the body carrying out regional state construction supervision


# 24190803375581
Unscheduled inspection
Start date: 2019-03-20, end date: —, duration:
Authority:
Purpose of inspection:


# 241902525289
Unscheduled inspection
Start date: 2019-02-21, end date: —, duration:
Authority:
Purpose of inspection:


# 241902471530
Unscheduled inspection
Start date: 2019-02-01, end date: 2019-02-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 04102016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of an investment facility, as well as the results of such work, with the requirements of the project documentation, including energy efficiency requirements, with the exception of capital construction facilities that are not subject to energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used. 72 Meeting the requirements set out in Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241902477417
Unscheduled inspection
Start date: 2019-02-05, end date: —, duration:
Authority:
Purpose of inspection:


# 241902482759
Unscheduled inspection
Start date: 2019-02-08, end date: —, duration:
Authority:
Purpose of inspection:


# 241902482743
Unscheduled inspection
Start date: 2019-02-08, end date: 2019-02-21, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction dated 04122018 4550OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 07022019 the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision


# 241902482727
Unscheduled inspection
Start date: 2019-02-08, end date: —, duration:
Authority:
Purpose of inspection:


# 241902432134
Unscheduled inspection
Start date: 2019-01-18, end date: —, duration:
Authority:
Purpose of inspection:


# 241902432130
Unscheduled inspection
Start date: 2019-01-18, end date: 2019-01-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked dated 06/122018 4719OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 17.012019. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7. The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision


# 241902432126
Unscheduled inspection
Start date: 2019-01-18, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241802375985
Unscheduled inspection
Start date: 2018-12-29, end date: 2019-02-04, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 312 dated 21122018 on the start of construction of the capital construction facility. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. 7 The subject of this audit is 71 Verification of compliance with the works and construction materials used during the construction of a capital construction facility, as well as the results of such work, to the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and to the requirements for equipping a capital construction facility with metering devices for used energy resources 72 Meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code Code of the Russian Federation 73 Checking the availability of a building permit


# 241802210695
Unscheduled inspection
Start date: 2018-12-10, end date: 2019-01-14, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 279 dated 03/122018 on the completion of the construction of the capital construction facility. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. 7 The subject of this audit is 71 Verification of compliance with the works and construction materials used during the construction of a capital construction facility, as well as the results of such work, meet the requirements of project documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, all acts regulations notices on the elimination of violations deficiencies identified during implementation of regional state construction supervision 72 Compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Verification of the availability of a building permit


# 241802105558
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-12-06, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the instruction dated 04102018 3810OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 22112018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241802105552
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-12-06, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the instruction issued earlier to the person being checked dated 04102018 3808OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 22112018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241802105572
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-12-06, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction dated 04102018 3812OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 22112018 the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision


# 241802046625
Unscheduled inspection
Start date: 2018-11-07, end date: —, duration:
Authority:
Purpose of inspection:


# 241802046535
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-12-04, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 275 dated 29102018 on the start of construction of the capital construction facility. The objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation. 7 The subject of this audit is 71 Verification of compliance with works and construction materials used during the construction of a capital construction facility, as well as the results of such work, to the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and to the requirements for equipping a capital construction facility with metering devices for used energy resources 72 Compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code Code of the Russian Federation 73 Checking the availability of a building permit


# 241802046519
Unscheduled inspection
Start date: 2018-11-07, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241802095922
Unscheduled inspection
Start date: 2018-11-12, end date: 2018-11-23, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose is to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the results of a preliminary check on the failure to eliminate violations specified in the regulation dated 26062018 108DS within the prescribed time frame Tasks to establish the fact of eliminating previously identified violations to verify the work actually performed in accordance with the prescribed measures within the prescribed time period subject to compliance with the instructions of state control bodies supervision


# 241801760673
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-10-18, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 16072018 2474OZHS on the elimination of identified violations at the specified capital construction facility, which expires on 04102018, previously issued to the person being checked. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision


# 241801123430
Unscheduled inspection
Start date: 2018-09-12, end date: 2018-10-09, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 118 dated 04092018 on the completion dates of works subject to inspection during the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. 7 The subject of this inspection is 71 Checking the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used 72 Meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking for a building permit


# 241801609713
Unscheduled inspection
Start date: 2018-09-24, end date: —, duration:
Authority:
Purpose of inspection:


# 241801609708
Unscheduled inspection
Start date: 2018-09-25, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241801609711
Unscheduled inspection
Start date: 2018-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 241800670006
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 04102016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800749856
Unscheduled inspection
Start date: 2018-08-30, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241800615419
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-09-03, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 119 dated 03082018 on the completion of the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation. 7 The subject of this inspection is 71 Verification of compliance with all acts prescriptions notices on the elimination of violations deficiencies identified during the implementation of regional state construction supervision 72 are subject to verification in accordance with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used. parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Verification of the availability of a building permit


# 241800624219
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-30, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The audit is carried out in order to carry out state supervision over compliance with legislation in the field of shared-equity construction of apartment buildings and or other real estate objects in connection with a complaint about improper fulfillment of obligations by the developer during the construction of a capital construction object. The objectives of this audit are to prevent identify and suppress violations of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects. The purpose of the audit is to ensure compliance with mandatory requirements and or requirements established by municipal legal acts


# 241800495575
Unscheduled inspection
Start date: 2018-07-04, end date: —, duration:
Authority:
Purpose of inspection:


# 241800553546
Unscheduled inspection
Start date: 2018-07-20, end date: —, duration:
Authority:
Purpose of inspection:


# 241800494672
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-27, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 26072017 inspections during the construction of the capital construction facility The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code Verification of the availability of a building permit in the Russian Federation


# 241800491027
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration:
Authority:
Purpose of inspection:


# 241800475370
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-07-13, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose is to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the results of a preliminary check on the failure to eliminate violations specified in regulation No. 131117 250DS within the prescribed time frame tasks are to establish the fact of elimination of violations detected earlier, to verify the work actually performed in accordance with the prescribed measures within the prescribed time frame, subject to compliance with the instructions of state control bodies


# 241800455558
Unscheduled inspection
Start date: 2018-06-15, end date: 2018-06-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited regulation No. 19042018 1048OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 14062018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800473617
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-07-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited order dated 29052018 1629EN on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 21062018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800469625
Unscheduled inspection
Start date: 2018-06-22, end date: 2018-07-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 07052018 1098OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 21062018 the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the authority carrying out regional state construction supervision


# 241800405931
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 10052017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800399925
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 04102016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800399660
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 04102016 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800384611
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 26072017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800384070
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 26072017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800363039
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-06-13, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 53 dated 08052018 on the completion dates of works subject to inspection during the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. 7 The subject of this inspection is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking for a building permit


# 241800363011
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-06-13, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 52 dated 08052018 on the completion dates of works subject to inspection during the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. 7 The subject of this inspection is 71 Checking the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used 72 Meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking for a building permit


# 241800438563
Unscheduled inspection
Start date: 2018-05-24, end date: 2018-06-21, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: The purpose is to carry out state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects based on the results of a preliminary check on the failure to eliminate violations specified in regulation No. 13112017 250DS within the established time frame. Objectives are to establish the fact of eliminating previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed time period. Subject is to comply with the instructions of the state control and supervision authorities


# 241800342413
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 26072017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800257607
Unscheduled inspection
Start date: 2018-04-06, end date: 2018-05-07, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification 66 dated 29032018 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation. 7 The subject of this inspection is 71 Verification of compliance with works and construction materials used during the construction of a capital construction facility, as well as the results of such work, requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with energy metering devices 72 Meeting the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a construction permit


# 241800244636
Unscheduled inspection
Start date: 2018-04-06, end date: 2018-04-19, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited order No. 14022018 55OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 05042018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800215047
Unscheduled inspection
Start date: 2018-03-23, end date: —, duration:
Authority:
Purpose of inspection:


# 24180803060401
Unscheduled inspection
Start date: 2018-02-02, end date: 2018-02-15, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited order dated 07112017 4834OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 01022018 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is to comply with the instructions of the authority carrying out regional state construction supervision


# 241800011564
Unscheduled inspection
Start date: 2018-01-26, end date: 2018-02-08, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: establishment of the fact of elimination of previously identified violations verification of the work actually performed in accordance with the prescribed measures within the prescribed period


# 24170802903255
Unscheduled inspection
Start date: 2017-12-01, end date: —, duration:
Authority:
Purpose of inspection:


# 24170802937030
Unscheduled inspection
Start date: 2017-12-11, end date: 2017-12-22, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 17112017 4989EN previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 08/122017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170802775587
Unscheduled inspection
Start date: 2017-11-03, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170802775494
Unscheduled inspection
Start date: 2017-11-03, end date: 2017-11-17, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28082017 3447OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 02112017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170802771416
Unscheduled inspection
Start date: 2017-11-01, end date: 2017-11-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 10052017 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Verification of a construction permit, Verification of a certificate of admission to the types of work on the construction of the facility capital construction projects that have an impact on the safety of the capital construction facility


# 24170802771409
Unscheduled inspection
Start date: 2017-11-01, end date: 2017-11-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 10052017 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Verification of a construction permit, Verification of a certificate of admission to the types of work on the construction of the facility capital construction projects that have an impact on the safety of the capital construction facility


# 24170802763875
Unscheduled inspection
Start date: 2017-11-01, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170802864154
Unscheduled inspection
Start date: 2017-11-17, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170802830618
Unscheduled inspection
Start date: 2017-11-17, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170802638693
Unscheduled inspection
Start date: 2017-10-06, end date: 2017-10-19, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction issued earlier to the person being checked from 13072017 2766OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 05102017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170802705929
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: Purpose implementation of state control and supervision in the field of shared-equity construction of apartment buildings and or other real estate objects on the basis of a reasoned submission dated 28092017 g 233 Tasks prevention identification and suppression of violations of legislation in the field of shared-equity construction of apartment buildings and or other real estate objects Subject to compliance with mandatory requirements and or requirements established by municipal legal acts


# 24170802619199
Unscheduled inspection
Start date: 2017-10-02, end date: 2017-10-27, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 10052017 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Verification of a construction permit, Verification of a certificate of admission to the types of work on the construction of the facility capital construction projects that have an impact on the safety of the capital construction facility


# 24170802612174
Unscheduled inspection
Start date: 2017-10-02, end date: —, duration:
Authority:
Purpose of inspection:


# 24170802682928
Unscheduled inspection
Start date: 2017-10-20, end date: 2017-11-02, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 21092017 3798OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 19102017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170802563147
Unscheduled inspection
Start date: 2017-09-29, end date: 2017-10-12, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28082017 3447EN previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 28092017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period


# 24170801914368
Unscheduled inspection
Start date: 2017-09-04, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170802405541
Unscheduled inspection
Start date: 2017-09-22, end date: —, duration:
Authority:
Purpose of inspection:


# 24170802405516
Unscheduled inspection
Start date: 2017-09-22, end date: —, duration:
Authority:
Purpose of inspection:


# 24170802405496
Unscheduled inspection
Start date: 2017-09-22, end date: 2017-10-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the previously issued to the person being audited instruction No. 28082017 3447OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 21092017 the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this audit is to comply with the instructions of the body carrying out Regional State construction supervision


# 24170802397900
Unscheduled inspection
Start date: 2017-09-22, end date: 2017-10-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 27072017 2807OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 21092017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out regional State construction supervision


# 24170801936904
Unscheduled inspection
Start date: 2017-08-30, end date: 2017-09-26, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 22082017 bx 185 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and design documentation, to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used, Verify the availability of a certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the capital construction facility


# 24170701843297
Unscheduled inspection
Start date: 2017-08-01, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701843319
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 10052017 inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation7 The subject of this audit is71 Checking the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources 72 Checking the availability of a construction permit 73 Checking the availability of a certificate of admission to the types of works on the construction of a capital construction facility that have an impact on the safety of the capital construction facility


# 24170701816777
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-08-21, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 17072017 bx 158 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation7 The subject of this inspection is71 Verification of the conformity of work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used72 Verification of the availability of a certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the capital construction facility


# 24170701816722
Unscheduled inspection
Start date: 2017-07-25, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170701816701
Unscheduled inspection
Start date: 2017-07-25, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701816809
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-08-21, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 17072017 bx 159 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and project documentation7 The subject of this inspection is71 Verification of the conformity of work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used72 Verification of the availability of a certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the capital construction facility


# 24170701736758
Unscheduled inspection
Start date: 2017-07-03, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701729640
Unscheduled inspection
Start date: 2017-07-03, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170701776270
Unscheduled inspection
Start date: 2017-07-21, end date: 2017-08-03, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 13062017 2426OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires in 2007-2017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170701664553
Unscheduled inspection
Start date: 2017-06-09, end date: 2017-06-23, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 28042017 1181OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 08062017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170701654685
Unscheduled inspection
Start date: 2017-06-02, end date: 2017-06-16, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 10042017 1262OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 01062017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out regional State construction supervision


# 24170701714978
Unscheduled inspection
Start date: 2017-06-23, end date: 2017-07-06, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is carried out in order to verify the fulfillment of the previously issued to the person being audited instruction from 19052017 1974OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 22062017the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this audit is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170701714965
Unscheduled inspection
Start date: 2017-06-23, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701675718
Unscheduled inspection
Start date: 2017-06-01, end date: 2017-06-15, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of an internal memo dated 25052017 bx bn containing information about the fact of a threat to harm the life health of citizens the environment property of individuals and legal entities in violation of urban planning legislation, including technical regulations and project documentation. The objectives of this inspection are to prevent identification and suppression of violations of legislation on urban development, including technical regulations and design documentation Verification of compliance of work performed and construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources Verification availability of a construction permit Verification of the availability of a certificate of admission to the types of work on the construction of a capital construction facility that affect the safety of the capital construction facility


# 24170701646010
Unscheduled inspection
Start date: 2017-06-01, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701564843
Unscheduled inspection
Start date: 2017-05-12, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170701584864
Unscheduled inspection
Start date: 2017-05-05, end date: 2017-06-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 26042017 bx 90 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and design documentation, to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used, Verify the availability of a certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the capital construction facility


# 24170701584854
Unscheduled inspection
Start date: 2017-05-05, end date: 2017-06-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 26042017 bx 89 on the start of construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities, including technical regulations and design documentation, to verify the compliance of the work and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for the energy resources used, Verify the availability of a certificate of admission to the types of work on the construction of the capital construction facility that affect the safety of the capital construction facility


# 24170701525613
Unscheduled inspection
Start date: 2017-05-05, end date: 2017-05-22, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28032017 1081OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 04052017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out the regional State construction supervision


# 24170701525589
Unscheduled inspection
Start date: 2017-05-05, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 24170701549819
Unscheduled inspection
Start date: 2017-05-02, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701513374
Unscheduled inspection
Start date: 2017-04-07, end date: 2017-04-20, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the previously issued to the person being audited instruction No. 10032017 519EN on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 06042017 The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this audit is to comply with the instructions of the body carrying out Regional State construction supervision


# 24170701501570
Unscheduled inspection
Start date: 2017-04-07, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701497751
Unscheduled inspection
Start date: 2017-04-03, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701493318
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 16022017 inspections during the construction of the capital construction facility The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, Verification of the availability of a certificate of admission to the types of work on the construction of the capital construction facility that have an impact on the safety of the capital construction facility


# 24170701492885
Unscheduled inspection
Start date: 2017-04-03, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701520700
Unscheduled inspection
Start date: 2017-04-21, end date: 2017-05-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 28022017 312OZHS previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 20042017. The objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision


# 24170701520403
Unscheduled inspection
Start date: 2017-04-21, end date: 2017-05-05, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked dated 01032017 22OZHS on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 20042017the objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this audit is the fulfillment of the instruction of the body carrying out the regional State construction supervision


# 24170701426606
Unscheduled inspection
Start date: 2017-03-17, end date: 2017-03-30, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is carried out in order to verify the fulfillment of the previously issued to the person being audited instruction No. 146OZHS dated 31.012017 on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 16032017. The objectives of this audit are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this audit is to comply with the instructions of the body carrying out Regional State construction supervision


# 24170701388982
Unscheduled inspection
Start date: 2017-03-01, end date: 2017-03-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 20072016 inspections during the construction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 24170701463765
Unscheduled inspection
Start date: 2017-03-20, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701381552
Unscheduled inspection
Start date: 2017-02-15, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701313273
Unscheduled inspection
Start date: 2017-02-28, end date: —, duration:
Authority:
Purpose of inspection:


# 24170701350196
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This audit is conducted in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation. The purpose of this audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the availability of a construction permit, verification of the availability of a certificate of admission to the types of work on the construction of the capital construction facility which have an impact on the safety of the capital construction facility


# 24170701350097
Unscheduled inspection
Start date: 2017-02-01, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.