Found 28 inspections:

# 772005237730
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-12-18, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision


# 771904070339
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify compliance with the instructions of the Moscow State Construction Supervision


# 77190803491740
Unscheduled inspection
Start date: 2019-09-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803450182
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803411174
Unscheduled inspection
Start date: 2019-05-13, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803270343
Unscheduled inspection
Start date: 2018-11-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803259539
Unscheduled inspection
Start date: 2018-11-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803250300
Unscheduled inspection
Start date: 2018-10-10, end date: 2018-10-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803232134
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803185342
Unscheduled inspection
Start date: 2018-07-31, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803134010
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802830408
Unscheduled inspection
Start date: 2017-11-13, end date: 2017-11-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802714371
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-10-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701802404
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-07-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701802834
Unscheduled inspection
Start date: 2017-07-12, end date: 2017-07-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701793031
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-07-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701668767
Unscheduled inspection
Start date: 2017-06-06, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701602883
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701592073
Unscheduled inspection
Start date: 2017-05-05, end date: 2017-05-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701465770
Unscheduled inspection
Start date: 2017-03-15, end date: 2017-03-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701459297
Unscheduled inspection
Start date: 2017-03-14, end date: 2017-03-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701298494
Unscheduled inspection
Start date: 2017-01-13, end date: 2017-01-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701322443
Unscheduled inspection
Start date: 2017-01-25, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701130730
Unscheduled inspection
Start date: 2016-11-18, end date: 2016-11-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701138020
Unscheduled inspection
Start date: 2016-11-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77160700991118
Unscheduled inspection
Start date: 2016-10-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77160601787465
Unscheduled inspection
Start date: 2016-08-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77160601696576
Unscheduled inspection
Start date: 2016-07-07, end date: 2016-07-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 600816 ot 07062016