# 741904046171
Unscheduled inspection
Start date: 2019-12-16, end date: 2019-12-20, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the installation of the gas pipeline along Partizanskaya Street, Beregovaya Street, the installation of supply lines to residential buildings and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Articles 49 of this Code and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used2 The availability of a construction permit 3 Meeting the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 741800298634
Unscheduled inspection
Start date: 2018-04-23, end date: 2018-04-27, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the earthworks for the installation of the GRP gas pipeline installation, testing of the gas pipeline, the layout of the reclamation pipeline route and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation


# 74170802804684
Unscheduled inspection
Start date: 2017-11-03, end date: 2017-11-09, duration:
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the preparation of the route, the preparation of the trench, the welding of lashes, the laying of the gas pipeline, the backfilling of the gas pipeline, the tests of the gas pipeline and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations of the project documentation2 The presence of a construction permit 3 Compliance with the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation