Found 9 inspections:

# 762101368854
Unscheduled inspection
Start date: 2021-11-25, end date: —, duration:
Authority:
Purpose of inspection:


# 762100175731
Unscheduled inspection
Start date: 2021-05-17, end date: —, duration: 6
Authority: Departament stroitelstva YAroslavskoi oblasti
Purpose of inspection: The purpose of this audit is to verify compliance with the mandatory requirements established by the legislation of the Russian Federation on participation in the shared-equity construction of apartment buildings and (or) other real estate objects.; The objectives of this audit are: to establish the fact that the developer deviated from the approximate schedule for the implementation of a construction project for six months or more during the construction of a residential building at 7 Malaya Proletarskaya str., Yaroslavl, the construction of which is being carried out by ISC MIK LLC (reporting by the developer on activities related to attracting funds from equity participants construction for the construction (creation) of apartment buildings and (or) other real estate objects, received by the regulatory authority on 03/24/2021 for No. 03/005/27195 in the Unified Housing Construction Information System). The subject of this audit is the developer's documentation for compliance with the mandatory requirements established by the legislation of the Russian Federation on participation in the shared–equity construction of apartment buildings and (or) other real estate objects.


# 762000171541
Unscheduled inspection
Start date: 2021-04-28, end date: 2020-10-14, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The verification is carried out for the purpose of: based on the verification program; The objectives of this audit are: to determine the compliance of the work performed during the construction of a capital construction facility with the requirements of the project documentation. The subject of this audit is: compliance with mandatory requirements.


# 762005181727
Unscheduled inspection
Start date: 2020-10-14, end date: —, duration:
Authority:
Purpose of inspection:


# 762004381759
Unscheduled inspection
Start date: 2020-03-26, end date: 2020-03-26, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the verification program, the objectives of this audit are to determine the compliance of the work performed during the construction of a capital construction facility with the requirements of the design documentation. The subject of this audit is the observance of mandatory requirements


# 762004199790
Unscheduled inspection
Start date: 2020-01-17, end date: 2020-01-17, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The inspection is carried out in order to determine, on the basis of the verification program, the objectives of this inspection are to determine whether the work performed during the construction of a capital construction facility meets the requirements of project documentation


# 761903882136
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-10-23, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation. The subject of this audit is compliance with mandatory requirements


# 761902708488
Unscheduled inspection
Start date: 2019-04-29, end date: 2019-04-29, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The inspection is carried out in order to verify the fulfillment of regulation 1 of 21032019 of the notification on the elimination of violations of 04042019the tasks of this inspection are to determine the compliance of work performed during the construction of a capital construction facility with the requirements of the draft construction organization project. The purpose of this inspection is to comply with mandatory requirements


# 761902587185
Unscheduled inspection
Start date: 2019-03-21, end date: 2019-03-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: Based on the inspection program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of the design documentation. The subject of this audit is compliance with mandatory requirements


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.