Found 7 inspections:

# 782101375282
Unscheduled inspection
Start date: 2021-11-17, end date: —, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: purpose: to determine the compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for the energy resources used . The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer. During the construction and reconstruction of capital construction facilities, the requirements of the project documentation are met. The subject of this inspection is: verification of the completed construction of the facility to the requirements of the design documentation, including fire-fighting measures, measures to ensure the sanitary and epidemiological welfare of the population, and environmental protection.


# 782100360402
Unscheduled inspection
Start date: 2021-07-20, end date: —, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: To establish that this inspection is carried out for the purpose of: verifying compliance with the requirements of Regulation No. 2/247Pr7-20 dated 04.12.2020 The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of the project documentation performed during construction, reconstruction of capital construction facilities. 7. The subject of this audit is: compliance of the work performed and the building materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (subject to changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code; - availability of a building permit; - fulfillment of the requirements established by Parts 2, 3 and 3.1 of Article 52 of this Code.


# 782005191770
Unscheduled inspection
Start date: 2020-11-09, end date: —, duration:
Authority:
Purpose of inspection:


# 782005108972
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration:
Authority:
Purpose of inspection:


# 781901979728
Unscheduled inspection
Start date: 2019-02-14, end date: 2019-03-07, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance of the completed works with the project foundation and foundations


# 781801991752
Unscheduled inspection
Start date: 2018-10-17, end date: 2018-10-31, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance with regulation 22574Pr3318 of 07092018


# 781800618492
Unscheduled inspection
Start date: 2018-08-14, end date: 2018-09-14, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: verification of compliance of the performed works on the organization of the construction site with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation


Information about inspections