# 142101334295
Unscheduled inspection
Start date: 2021-11-17, end date: 2021-11-30, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: in connection with the notification No. 3 of November 08, 2021 received by the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia) (ex.no. from): a) compliance of the constructed capital construction facility with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used; b) elimination by the developer, technical customer, construction person identified during construction control and state construction supervision of all violations of compliance of completed works with regulatory requirements acts and design documentation; c) execution of executive documentation related to the performance of all construction works, as well as the use of building materials (products), prevention, detection and suppression of violations of the law committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor) on urban planning activities, including project documentation., compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 142101334055
Unscheduled inspection
Start date: 2021-11-17, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 142100376192
Unscheduled inspection
Start date: 2021-07-26, end date: 2021-07-30, duration: 5
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), on October 23, 2020, compliance with the construction of the capital construction facility by the developer, the technical customer, the person carrying out the construction, mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction, reconstruction of the capital construction facility prevention, detection and suppression of violations of the legislation on urban development, including project documentation, committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor), compliance with mandatory requirements and (or) requirements established by municipal legal acts;
# 142100376122
Unscheduled inspection
Start date: 2021-07-26, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:
# 142100294637
Unscheduled inspection
Start date: 2021-06-22, end date: 2021-06-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), dated 03/19/2021, compliance with the construction of the capital construction facility by the developer, the technical customer, the person carrying out the construction, mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction, reconstruction of the capital construction facility compliance with mandatory requirements and (or) requirements established by municipal legal acts; compliance of the information contained in the notification of the commencement of certain types of entrepreneurial activity with mandatory requirements; compliance of the information contained in the application and documents of a legal entity or individual entrepreneur for the provision of legal status, special permission (license) for the right to carry out certain types of activities or permits (approvals) for the implementation of other legally significant actions, if the conduct of an appropriate unscheduled inspection of a legal entity, an individual entrepreneur is provided for by the rules for granting legal status, special permission (license), issuance of permits (approvals) to mandatory requirements, as well as data on these legal entities and individual entrepreneurs contained in the unified state register of legal entities individuals, the unified state register of individual entrepreneurs and other federal information resources; compliance with the instructions of state control (supervision) bodies, municipal control bodies; holding events: to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents, having a special historical, scientific, cultural significance, which is part of the national library fund; to prevent the occurrence of emergency situations of a natural and man-made nature; to ensure the security of the state; to eliminate the consequences of causing such harm.
# 142100126960
Unscheduled inspection
Start date: 2021-04-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142100131999
Unscheduled inspection
Start date: 2021-04-22, end date: 2021-05-07, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), 10/22/2021, compliance with the construction of the capital construction facility by the developer, the technical customer, the person carrying out the construction, mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction, reconstruction of the capital construction facility, prevention, detection and suppression of violations of the legislation on urban development, including project documentation, legal acts committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer (hereinafter referred to as the contractor); compliance of the information contained in the notification of the commencement of certain types of entrepreneurial activity with mandatory compliance with the information contained in the application and documents of a legal entity or individual entrepreneur for granting legal status, a special permit (license) for the right to carry out certain types of activities or permission (approval) for other legally significant actions, if conducting an appropriate unscheduled inspection of a legal entity, individual entrepreneur is provided for by the rules for granting legal status, special permits (licenses), issuance of permits (approvals) to mandatory requirements, as well as data on these legal entities and individual entrepreneurs contained in the unified state register of legal entities, the unified state register of individual entrepreneurs and other federal information resources; compliance with the instructions of state control (supervision) bodies, municipal control bodies; holding events: to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents, of special historical, scientific, cultural significance, which are part of the national library fund; to prevent the occurrence of emergency situations of a natural and man-made nature; to ensure the security of the state; to eliminate the consequences of causing such harm
# 142005226241
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-12-02, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: Subject of inspection in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha Yakutia on October 22, 2020, compliance with the construction of a capital construction facility by the developer, the technical customer, the person carrying out the construction of mandatory requirements in the field of construction and applied building materials products of the established procedure for the construction of reconstruction of the capital construction facility 1 compliance with the performance of works and applied building materials in in the process of construction reconstruction of a capital construction facility as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of information models are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142005226239
Unscheduled inspection
Start date: 2020-11-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142005226224
Unscheduled inspection
Start date: 2020-11-19, end date: 2020-12-16, duration: 20
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The subject of verification in connection with notification 3 received by the Department of State Construction and Housing Supervision of the Republic of Sakha Yakutia dated October 30, 2020, vx 8068 dated October 30, 2020 a compliance of the constructed capital construction facility with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used b elimination by the developer of technical the customer is a person engaged in construction identified during construction control and state construction supervision of all violations of compliance of completed works with the requirements of regulatory legal acts and project documentation in the design of executive documentation related to the performance of all construction work as well as the use of building materials products
# 141903922519
Unscheduled inspection
Start date: 2019-11-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141902955019
Unscheduled inspection
Start date: 2019-08-21, end date: 2019-08-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: this inspection is carried out in order to verify, in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha Yakutia on March 29, 2019, compliance with the construction of the capital construction facility by the developer, the technical customer, the person carrying out the construction of mandatory requirements in the field of construction and used building materials products of the established procedure for construction reconstruction of the capital construction facility 1 compliance with the performance of works and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work meet the requirements of the design documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 of Article 52 of the Urban Planning Code The Code of the Russian Federation
# 141902776864
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-05-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, Subject to verification 1 compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 6 of Article 52 of the Urban Planning Code of the Russian Federation
# 141902701046
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-05-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 6 of Article 52 of the Urban Planning Code of the Russian Federation
# 14170701894691
Unscheduled inspection
Start date: 2017-08-25, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701794439
Unscheduled inspection
Start date: 2017-06-28, end date: 2017-07-12, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, for compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by the developer or the technical customer on the basis of the contract of an individual or legal entity According to the order
# 14170701719643
Unscheduled inspection
Start date: 2017-06-28, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 14170701723602
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor
# 14170701723566
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 14170701492393
Unscheduled inspection
Start date: 2017-03-30, end date: 2017-04-26, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation1 committed by the developer, the technical customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, for compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations and project documentation including the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources2 availability of a construction permit 3 compliance with the requirements of parts 236 of Article 52 of the Urban Planning Code of the Russian Federation availability of a certificate of admission to construction reconstruction works that affect the safety of capital construction facilities, including a certificate of admission to work on the organization of construction in case of involvement by a developer or a technical customer on the basis of an agreement between an individual or a legal entity under the inspection program