# 772101482455
Unscheduled inspection
Start date: 2021-12-20, end date: 2021-12-30, duration: 9
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772101239377
Unscheduled inspection
Start date: 2021-10-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004435103
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771904085571
Unscheduled inspection
Start date: 2019-12-11, end date: 2019-12-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803441593
Unscheduled inspection
Start date: 2019-06-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803308166
Unscheduled inspection
Start date: 2018-12-27, end date: 2019-01-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803135988
Unscheduled inspection
Start date: 2018-05-11, end date: 2018-05-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802807031
Unscheduled inspection
Start date: 2017-11-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701674033
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-06-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701582526
Unscheduled inspection
Start date: 2017-05-02, end date: 2017-05-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77160701069744
Unscheduled inspection
Start date: 2016-11-07, end date: 2016-11-11, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 1106416 ot 17102016
# 77160701051739
Unscheduled inspection
Start date: 2016-10-27, end date: 2016-11-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 676716 ot 01072016