# 762101475590
Unscheduled inspection
Start date: 2021-12-20, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu: na osnovanii programmy provedeniya proverok.
zadachami nastoyaschei proverki yavlyayutsya:
opredelenie sootvetstviya rabot, vypolnennyh pri stroitelstve obekta kapitalnogo stroitelstva, trebovaniyam proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya:
soblyudenie obyazatelnyh trebovanii.
# 762100851095
Unscheduled inspection
Start date: 2021-09-24, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu: na osnovanii programmy provedeniya proverok.
zadachami nastoyaschei proverki yavlyayutsya:
opredelenie sootvetstviya rabot, vypolnennyh pri stroitelstve obekta kapitalnogo stroitelstva, trebovaniyam proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya:
soblyudenie obyazatelnyh trebovanii.
# 762100215963
Unscheduled inspection
Start date: 2021-05-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 762100215942
Unscheduled inspection
Start date: 2021-05-20, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu: na osnovanii programmy provedeniya proverok.
zadachami nastoyaschei proverki yavlyayutsya:
opredelenie sootvetstviya rabot, vypolnennyh pri stroitelstve obekta kapitalnogo stroitelstva, trebovaniyam proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya:
soblyudenie obyazatelnyh trebovanii.
# 762100088893
Unscheduled inspection
Start date: 2021-04-02, end date: 2021-04-06, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: This audit is conducted for the purpose of:
based on the audit program;
The objectives of this audit are:
to determine the compliance of the work performed during the construction of a capital construction facility with the requirements of the project documentation
The subject of this audit is:
compliance with mandatory requirements.