# 741802016059
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-11-12, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the construction of the roadbed, the installation of a foundation made of crushed stone by the method of jamming, the installation of a lower layer of asphalt concrete coating, the installation of an upper layer of asphalt concrete coating, the construction of roadsides, the construction of artificial structures, the construction of roads and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation 2 Availability of a construction permit 3 Meeting the requirements of hh 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741802016001
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-11-12, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the construction of 3-point reinforced concrete pipes d = 15 m with the device of the underlying layer of crushed stone fr 4070 to the device of the base of fractionated crushed stone by jamming to the device of the lower coating layer of a hot porous coarse-grained ab mixture of grade I to the device of the upper coating layer of a hot dense fine-grained ab mixture of type B grade III to the device of roadsides to the device of ramps to the device of the landing pad the construction of the road and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 ct52 of the Urban Planning Code of the Russian Federation
# 741800856081
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-09-12, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work performed on the device of the underlying layer of crushed stone fr 4070 to the device of the base of fractionated crushed stone by jamming to the device of the lower coating layer of a hot porous coarse-grained ab mixture of grade I to the device of the upper coating layer of a hot dense fine-grained ab mixture of type B grade III to the device of roadsides to the device of ramps to the device of a landing pad to the construction of 3-point reinforced concrete pipes d =15 m the construction of the road and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 ct52 of the Urban Planning Code of the Russian Federation
# 741800857169
Unscheduled inspection
Start date: 2018-09-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800855823
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-09-12, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work performed on the device of the underlying layer of crushed stone fr 4070 to the device of the base of fractionated crushed stone by jamming to the device of the lower coating layer of a hot porous coarse-grained ab mixture of grade I to the device of the upper coating layer of a hot dense fine-grained ab mixture of type B grade III to the device of roadsides to the device of ramps to the device of a landing pad to the construction of 3-point reinforced concrete pipes d =15 m the construction of the road and the construction materials used during the construction of the capital construction facility, as well as the results of such work, the requirements of the technical regulations of the project documentation 2 The availability of a construction permit 3 Compliance with the requirements of hh 23 and 31 ct52 of the Urban Planning Code of the Russian Federation
# 741800607817
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-15, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on the construction of the earth bed, the construction of reinforced concrete pipes d =1 m, the device of the underlying layer of crushed stone fr 4070, the device of the base of fractionated crushed stone by the jamming method, the construction of 3-point reinforced concrete pipes d=15 m and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation 2 Availability of permits for construction 3 Meeting the requirements of HH 23 and 31 st52 of the Urban Planning Code of the Russian Federation
# 741800530297
Unscheduled inspection
Start date: 2018-07-11, end date: —, duration: —
Authority: —
Purpose of inspection: