Found 7 inspections:

# 242004344302
Unscheduled inspection
Start date: 2020-03-13, end date: —, duration:
Authority:
Purpose of inspection:


# 241802051007
Unscheduled inspection
Start date: 2018-11-09, end date: —, duration:
Authority:
Purpose of inspection:


# 241800585981
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:


# 241800309910
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-31, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the reconstruction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 16082017 inspections during the reconstruction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the construction materials used during the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements set out in parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 241800026405
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-02-28, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 26072017 inspections during the construction of the capital construction facility the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation 7 The subject of this audit is 71 Verification of the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used 72 Compliance with the requirements established by parts 2 3 and 31 of the Article 52 of the Urban Planning Code of the Russian Federation 73 Checking the availability of a building permit


# 24170802762088
Unscheduled inspection
Start date: 2017-11-01, end date: 2017-11-29, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this audit is conducted in order to carry out regional state construction supervision during the reconstruction of the specified capital construction facility in connection with the timing of completion of work that is subject to verification in accordance with the approved program of 16082017 inspections during the reconstruction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation Verification of compliance of the work performed and the construction materials used during the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources Verification of a construction permit Verification of a certificate of admission to the types of work on the reconstruction of the facility capital construction projects that have an impact on the safety of the capital construction facility


# 24170701845621
Unscheduled inspection
Start date: 2017-08-03, end date: 2017-08-30, duration:
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 26072017 bx 118 on the completion dates of works subject to inspection during the construction of the capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation7 The subject of this inspection is71 Verification of compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources 72 Verification of a construction permit 73 Verification of a certificate of admission to the types of work on the construction of the capital construction facility which have an impact on the safety of the capital construction facility


Information about inspections