# 472005323806
Unscheduled inspection
Start date: 2020-12-24, end date: 2021-01-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the completion of the work provided for in the inspection program The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources. requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 472004474516
Unscheduled inspection
Start date: 2020-08-07, end date: 2020-09-03, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 472004437408
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-07-21, duration: 2
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 472004415414
Unscheduled inspection
Start date: 2020-05-27, end date: 2020-06-24, duration: 4
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 782004319927
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode SanktPeterburge
Purpose of inspection: Checking the technical specifications
# 472004343338
Unscheduled inspection
Start date: 2020-03-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004370892
Unscheduled inspection
Start date: 2020-03-19, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 472004269104
Unscheduled inspection
Start date: 2020-02-06, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471904074349
Unscheduled inspection
Start date: 2019-12-05, end date: 2020-01-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation
# 471903834925
Unscheduled inspection
Start date: 2019-10-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471904023705
Unscheduled inspection
Start date: 2019-01-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471802144337
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-12-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad region
# 471802079058
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-12-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471801321660
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-10-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the elimination of violations of mandatory requirements specified in the notice of the person carrying out the construction on the elimination of identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design, committed by the developer, the technical customer, the person carrying out the construction
# 471801950272
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-31, duration: —
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: THE Labor Code OF the Russian Federation
# 471800559881
Unscheduled inspection
Start date: 2018-07-16, end date: 2018-08-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471801950247
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: THE Labor Code OF the Russian Federation
# 471800383200
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-06-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction