# 162101430694
Unscheduled inspection
Start date: 2021-12-09, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/01/2021 case No. 14-04-2020/0029. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162101371496
Unscheduled inspection
Start date: 2021-11-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162101204635
Unscheduled inspection
Start date: 2021-10-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100733299
Unscheduled inspection
Start date: 2021-09-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100467818
Unscheduled inspection
Start date: 2021-08-19, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:
# 162100341975
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/17/2021 case No. 14-04-2020/0032. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100341933
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100151895
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-23, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 12/21/2020 case No. 14-04-2020/0032. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100151675
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-23, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/05/2021 case No. 14-04-2020/0029. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100040626
Unscheduled inspection
Start date: 2021-03-04, end date: 2021-03-05, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 02/05/2021 case No. 14-04-2020/0029. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162100026544
Unscheduled inspection
Start date: 2021-02-24, end date: 2021-02-26, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 12/21/2020 case No. 14-04-2020/0032. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this audit is compliance with mandatory requirements and/or requirements established by municipal legal acts.
# 162105320517
Unscheduled inspection
Start date: 2021-01-28, end date: —, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: