# 631800336670
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-11, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631800064491
Unscheduled inspection
Start date: 2018-02-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 63170701434051
Unscheduled inspection
Start date: 2017-03-15, end date: 2017-03-17, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29042016 notification dated 01032017 691 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63160701254301
Unscheduled inspection
Start date: 2016-12-26, end date: 2016-12-28, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Inspection program dated 29042016 notification dated 14122016 7003 Verification of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used
# 63160700124645
Unscheduled inspection
Start date: 2016-09-07, end date: —, duration: —
Authority: —
Purpose of inspection: