# 771902603023
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-26, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Proverka provoditsya s celyu zaschity prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya rabotnika ot 25022019 777641719OB o narushenii rabotodatelem ego trudovyh prav Zadachami proverki yavlyayutsya nadzor i kontrol za soblyudeniem zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami sootvetstvie svedenii soderzhaschihsya v uvedomlenii o nachale osuschestvleniya otdelnyh vidov predprinimatelskoi deyatelnosti obyazatelnym trebovaniyam sootvetstvie svedenii soderzhaschihsya v zayavlenii i dokumentah yuridicheskogo lica ili individualnogo predprinimatelya o predostavlenii pravovogo statusa specialnogo razresheniya licenzii vydachi razresheniya soglasovaniya obyazatelnym trebovaniyam a takzhe dannym ob ukazannyh yuridicheskih licah i individualnyh predprinimatelyah soderzhaschimsya v edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya provedenie meropriyatii po predotvrascheniyu prichineniya vreda zhizni zdorovyu grazhdan vreda zhivotnym rasteniyam okruzhayuschei srede obektam kulturnogo naslediya pamyatnikam istorii i kultury narodov Rossiiskoi Federacii muzeinym predmetam i muzeinym kollekciyam vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii dokumentam imeyuschim osoboe istoricheskoe znachenie nauchnoe kulturnoe znachenie vhodyaschim v sostav nacionalnogo bibliotechnogo fonda po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera po obespecheniyu bezopasnosti gosudarstva po likvidacii posledstvii prichineniya takogo vreda
# 771902527260
Unscheduled inspection
Start date: 2019-02-28, end date: 2019-03-28, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ot 26112018 73447618OB1210903 ob ustranenii vyyavlennyh narushenii trebovanii trudovogo zakonodatelstva i inyh normativnyh aktov soderzhaschih normy trudovogo prava Zadachami proverki yavlyayutsya nadzor i kontrol za soblyudeniem zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii i ili trebovanii ustanovlennyh municipalnymi pravovymi aktami sootvetstvie svedenii soderzhaschihsya v uvedomlenii o nachale osuschestvleniya otdelnyh vidov predprinimatelskoi deyatelnosti obyazatelnym trebovaniyam sootvetstvie svedenii soderzhaschihsya v zayavlenii i dokumentah yuridicheskogo lica ili individualnogo predprinimatelya o predostavlenii pravovogo statusa specialnogo razresheniya licenzii vydachi razresheniya soglasovaniya obyazatelnym trebovaniyam a takzhe dannym ob ukazannyh yuridicheskih licah i individualnyh predprinimatelyah soderzhaschimsya v edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya provedenie meropriyatii po predotvrascheniyu prichineniya vreda zhizni zdorovyu grazhdan vreda zhivotnym rasteniyam okruzhayuschei srede obektam kulturnogo naslediya pamyatnikam istorii i kultury narodov Rossiiskoi Federacii muzeinym predmetam i muzeinym kollekciyam vklyuchennym v sostav Muzeinogo fonda Rossiiskoi Federacii dokumentam imeyuschim osoboe istoricheskoe znachenie nauchnoe kulturnoe znachenie vhodyaschim v sostav nacionalnogo bibliotechnogo fonda po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera po obespecheniyu bezopasnosti gosudarstva po likvidacii posledstvii prichineniya takogo vreda
# 771801979379
Unscheduled inspection
Start date: 2018-10-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170803001807
Unscheduled inspection
Start date: 2017-12-18, end date: 2017-12-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802815648
Unscheduled inspection
Start date: 2017-11-07, end date: 2017-11-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802814693
Unscheduled inspection
Start date: 2017-11-07, end date: 2017-12-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802773642
Unscheduled inspection
Start date: 2017-10-26, end date: 2017-10-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701862246
Unscheduled inspection
Start date: 2017-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701857078
Unscheduled inspection
Start date: 2017-08-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701750165
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-07-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701537360
Unscheduled inspection
Start date: 2017-04-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701449390
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701315285
Unscheduled inspection
Start date: 2017-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701118904
Unscheduled inspection
Start date: 2016-11-15, end date: 2016-12-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: To establish that this audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program, the objectives of this audit are to prevent identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used