Found 6 inspections:

# 471904030397
Unscheduled inspection
Start date: 2019-11-25, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the verification of the work at the start of construction is to verify the work specified in the notice of the person carrying out the construction on the completion dates of the work that is subject to verification The subject of this verification is compliance with mandatory requirements, including compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy requirements compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation and the requirements for equipping the capital construction facility with metering devices for used energy resources the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471802064147
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-12-06, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: This inspection is carried out in order to control the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements 11111 dated 29032018 11112 dated 29032018


# 471800263297
Unscheduled inspection
Start date: 2018-04-04, end date: 2018-05-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the application of citizens, including individual entrepreneurs and legal entities, information from public authorities, officials of the state supervision authority, local governments, and the media. The subject of this audit is compliance with mandatory requirements, including compliance of the work performed and the construction materials used during the construction and reconstruction of a capital construction facility, as well as the results of such work with the requirements of technical regulations project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical violations, committed by the developer, the technical customer, the person carrying out the construction regulations and project documentation


# 471800238929
Unscheduled inspection
Start date: 2018-03-21, end date: —, duration:
Authority:
Purpose of inspection:


# 001800177567
Unscheduled inspection
Start date: 2018-03-06, end date: 2018-03-07, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Prevention detection and suppression of violations of mandatory requirements established by federal laws and other regulatory acts of the Russian Federation in the field of industrial safety taking measures provided for by the legislation of the Russian Federation to prevent and or eliminate the consequences of identified violations


# 47170701481802
Unscheduled inspection
Start date: 2017-03-27, end date: 2017-04-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the citizen's application The purpose of this audit is to comply with mandatory requirements, including compliance with the performance of work and the construction materials used during the construction and reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of Parts 2 and 3 of the article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.