# 002004330553
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-06, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to monitor the implementation of the instruction of the Siberian Directorate of Rostechnadzor 3408POZP40 dated 11072019, the deadline for which expires. The objectives of this inspection are the prevention, detection and suppression of violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations and rules for the protection of The labor subject of this audit is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001801685514
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to monitor the implementation of paragraphs 4 to 8 of the regulation of the Siberian Directorate of Rostechnadzor 3405PTSE37 3407PTSE23 dated 29062018, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations 7 The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001800585902
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-08-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 123567 of the regulation of the Siberian Directorate of Rostechnadzor 3405pTSE37 3407pTSE23 dated 29062018, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 00170802077712
Unscheduled inspection
Start date: 2017-09-06, end date: 2017-09-29, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 1 to 2 of the regulation of the Siberian Directorate of Rostechnadzor 3405POZP56 dated 01082017, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 00170701861397
Unscheduled inspection
Start date: 2017-08-11, end date: 2017-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 3 4 5 of the regulation of the Siberian Directorate of Rostechnadzor 3405POZP56 dated 01082017, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" technical regulations rules for the technical operation of heat supply facilities and For heat-consuming installations, the subject of this inspection is to note the necessary fulfillment of the instructions of the state control bodies, the supervision of municipal control bodies
# 00170701814264
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-08-15, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out as part of the implementation of the federal state energy supervision in the field of heat supply 313853436 To establish that this inspection is carried out in order to verify control over the progress of preparations for the operation of the limited liability company "Heat Supply Company "Orlovskaya" in the 2017-2018 OZP on the basis of the Order of the Federal Service for Environmental Technological and Nuclear Supervision 256 dated 10072017 issued in pursuance of the instruction Deputy Chairman of the Government of the Russian Federation DN Kozak dated 29062017 DKP94194 The objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this audit is to note the necessary warning, detection and suppression of violations heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by the Federal Law of 27072010 g 190FZ "On heat supply" technical regulations rules for the technical operation of heat supply facilities and heat-consuming installations
# 00160700279693
Unscheduled inspection
Start date: 2016-08-31, end date: 2016-09-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the progress of preparations for the work of JSC FGC Gaz Khimstroy Invest in the 2016-2017 OZP on the basis of Order No. 229 of the Federal Service for Environmental Technological and Nuclear Supervision dated 17062016 issued pursuant to the instructions of the Deputy Chairman of the Government of the Russian Federation DN Kozak dated 02062016 DKP93275
# 002004330553
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-06, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to monitor the implementation of the instruction of the Siberian Directorate of Rostechnadzor 3408POZP40 dated 11072019, the deadline for which expires. The objectives of this inspection are the prevention, detection and suppression of violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations and rules for the protection of The labor subject of this audit is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 002004301930
Unscheduled inspection
Start date: 2020-02-27, end date: 2020-02-28, duration: 2
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of a previously issued prescription
# 001902861377
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-08-02, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the progress of preparations for work in the autumn-winter period of 2019-2020 on the basis of the Order of the Head of the Federal Service for Environmental Technological and Nuclear Supervision AV Alyoshin dated 04072019 261 issued pursuant to the instructions of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 19062019 VMP95084 The objectives of this inspection are to verify the technical condition and safe operation of thermal power plants in order to control the progress of preparations for work in the autumn-winter period of 2019-2020, the subject of this audit is compliance with the mandatory requirements of the legislation of the Russian Federation and regulatory legal acts during the operation of thermal power plants
# 701902505092
Unscheduled inspection
Start date: 2019-02-15, end date: 2019-03-15, duration: —
Authority: Departament prirodnyh resursov i ohrany okruzhayuschei sredy Tomskoi oblasti
Purpose of inspection: verification of compliance with regulation No. 135 dated 13072018 on the elimination of identified violations of the law
# 001802161818
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose is to monitor the execution of the instruction of the Siberian Directorate of Rostechnadzor dated 29062018 24GS2018019, the deadline for which has expired
# 701802055646
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-11-29, duration: —
Authority: Gosudarstvennaya inspekciya truda v Tomskoi oblasti
Purpose of inspection: Implementation of state supervision over compliance with labor legislation protection of labor rights of an employee
# 001801685514
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to monitor the implementation of paragraphs 4 to 8 of the regulation of the Siberian Directorate of Rostechnadzor 3405PTSE37 3407PTSE23 dated 29062018, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations 7 The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001800585902
Unscheduled inspection
Start date: 2018-07-27, end date: 2018-08-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 123567 of the regulation of the Siberian Directorate of Rostechnadzor 3405pTSE37 3407pTSE23 dated 29062018, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 701800249594
Unscheduled inspection
Start date: 2018-02-01, end date: 2018-03-01, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: The purpose is to prevent as well as identify and suppress violations of urban planning legislation during an unscheduled on-site inspection of the execution of the regulation on the elimination of violations 15315PR2 dated 28112017 The task is to prevent as well as identify and suppress violations of urban planning legislation The subject is to comply with the regulations of state control bodies supervision of municipal control bodies
# 70170802803890
Unscheduled inspection
Start date: 2017-10-31, end date: 2017-11-28, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: The purpose is to prevent as well as identify and suppress violations of urban planning legislation during an unscheduled on-site inspection based on an appeal from the Department of Civil Engineering of Tomsk 01011911087 dated 28092017 reg 720763 dated 06102017 and an official memo from the head of the Construction Supervision Department of the State Tax Service of the Tomsk Region Marchenko AP dated 19102017 on the production of works at the facility in violation of the requirements of the organization of construction production, which poses a threat of harm harm to human life and health, the environment, the security of the state, the property of individuals and legal entities, the task is to prevent, identify and suppress violations of urban planning legislation, the subject is to comply with mandatory requirements and or requirements established by municipal legal acts, and the conformity of work performed and construction materials used during the construction, reconstruction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation
# 00170802077712
Unscheduled inspection
Start date: 2017-09-06, end date: 2017-09-29, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 1 to 2 of the regulation of the Siberian Directorate of Rostechnadzor 3405POZP56 dated 01082017, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this check is to note the necessary fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 00170701861397
Unscheduled inspection
Start date: 2017-08-11, end date: 2017-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the implementation of paragraphs 3 4 5 of the regulation of the Siberian Directorate of Rostechnadzor 3405POZP56 dated 01082017, the deadline for which has expired. The objectives of this inspection are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" technical regulations rules for the technical operation of heat supply facilities and For heat-consuming installations, the subject of this inspection is to note the necessary fulfillment of the instructions of the state control bodies, the supervision of municipal control bodies
# 00170701814264
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-08-15, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out as part of the implementation of the federal state energy supervision in the field of heat supply 313853436 To establish that this inspection is carried out in order to verify control over the progress of preparations for the operation of the limited liability company "Heat Supply Company "Orlovskaya" in the 2017-2018 OZP on the basis of the Order of the Federal Service for Environmental Technological and Nuclear Supervision 256 dated 10072017 issued in pursuance of the instruction Deputy Chairman of the Government of the Russian Federation DN Kozak dated 29062017 DKP94194 The objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations The subject of this audit is to note the necessary warning, detection and suppression of violations heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by the Federal Law of 27072010 g 190FZ "On heat supply" technical regulations rules for the technical operation of heat supply facilities and heat-consuming installations
# 70160700420793
Unscheduled inspection
Start date: 2016-09-15, end date: 2016-10-12, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: based on the inspection program dated 01042016 15315PP2
# 00160700279693
Unscheduled inspection
Start date: 2016-08-31, end date: 2016-09-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the progress of preparations for the work of JSC FGC Gaz Khimstroy Invest in the 2016-2017 OZP on the basis of Order No. 229 of the Federal Service for Environmental Technological and Nuclear Supervision dated 17062016 issued pursuant to the instructions of the Deputy Chairman of the Government of the Russian Federation DN Kozak dated 02062016 DKP93275