# 162004479403
Unscheduled inspection
Start date: 2020-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162004464898
Unscheduled inspection
Start date: 2020-07-29, end date: 2020-07-30, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program from 30062020 case 140420190013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004429374
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-06-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 13042020 case 140420190008 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the client, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 162004409552
Unscheduled inspection
Start date: 2020-05-21, end date: 2020-05-22, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with The inspection program dated 21012020 case 140420190013 The objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations and other regulatory legal acts and project documentation. The subject of this inspection is compliance with mandatory requirements and or requirements established by the Legislation of the Russian Federation. municipal legal acts
# 161903949177
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161903691472
Unscheduled inspection
Start date: 2019-10-03, end date: 2019-10-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts
# 161903014542
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-08-29, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied in the process of construction of the capital construction facility of building materials and the results of such works with the requirements of the design documentation prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, compliance with mandatory requirements or requirements established by municipal legal acts