# 631903139845
Unscheduled inspection
Start date: 2019-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 631902939778
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-23, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050804521 ot 20062019 izveschenie 3425 ot 05082019
# 631902939729
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-23, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631902975197
Unscheduled inspection
Start date: 2019-08-26, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 631902788120
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-20, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050802771 ot 19042019
# 631902653335
Unscheduled inspection
Start date: 2019-04-18, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection:
# 631902597084
Unscheduled inspection
Start date: 2019-03-28, end date: 2019-04-05, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631802185679
Unscheduled inspection
Start date: 2018-12-07, end date: 2018-12-10, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050811891 ot 26102018
# 631802186016
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-14, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631801652669
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-26, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 631800654127
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-08-29, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya ot 20062018 01050805611
# 631800456549
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-20, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Vypolnenie ranee vydannogo predpisaniya 01050803331 ot 26042018
# 631800261243
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-26, duration: —
Authority: Gosudarstvennaya inspekciya stroitelnogo nadzora Samarskoi oblasti
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations other regulatory legal acts and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used