Found 8 inspections:

# 782100169571
Unscheduled inspection
Start date: 2021-04-27, end date: —, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: To establish that this check is carried out in order to: Inspection of the completed capital construction facility. Completion of measures to meet the mandatory requirements of fire safety, sanitary and epidemiological safety, environmental safety; The objectives of this review are: Prevention, as well as detection and suppression of violations of compliance of works performed during construction, reconstruction of capital construction facilities with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this review is: Determination of compliance of the constructed capital construction facility with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used.


# 782005292547
Unscheduled inspection
Start date: 2020-12-28, end date: —, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection:


# 782005189546
Unscheduled inspection
Start date: 2020-10-19, end date: 2020-10-30, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance with the requirements in the field of environmental protection provided for in the project documentation, prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer, the customer, of compliance with the work performed during the construction reconstruction of capital construction facilities with the requirements of project documentation, compliance of the work performed at the capital construction facility with the requirements of project documentation in the field of environmental protection


# 782004493798
Unscheduled inspection
Start date: 2020-08-19, end date: 2020-09-11, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: To establish that this inspection is carried out in order to ensure Compliance of the work and construction materials used in the construction of a capital construction facility for the installation of enclosing structures roof facades window and door fillings and engineering networks as well as the results of such work the performance of indicators described in the construction permit the tasks of this inspection are prevention identification and suppression of violations committed by the developer the customer as well as the person carrying out construction on on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, violations of the legislation on urban planning and design documentationthe subject of this audit is to determine the compliance of the work performed with the construction materials used in the construction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation, the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 782004351742
Unscheduled inspection
Start date: 2020-03-12, end date: —, duration:
Authority:
Purpose of inspection:


# 781903935148
Unscheduled inspection
Start date: 2019-11-18, end date: —, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection:


# 781802079555
Unscheduled inspection
Start date: 2018-11-08, end date: 2018-12-05, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance of the completed works with the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation Prevention as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance of works performed during construction reconstruction of capital construction facilities with the requirements of technical regulations, other regulatory legal acts and project documentation of zero cycle work Foundations designs below otm +0000


# 781801780551
Unscheduled inspection
Start date: 2018-10-02, end date: —, duration:
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.