Found 28 inspections:

# 772100074512
Unscheduled inspection
Start date: 2021-03-18, end date: 2021-03-31, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772004460389
Unscheduled inspection
Start date: 2020-07-20, end date: 2020-07-31, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and requirements for the equipment of the capital construction facility with metering devices for used energy resources


# 772004412308
Unscheduled inspection
Start date: 2020-05-20, end date: 2020-05-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 772004337837
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004357136
Unscheduled inspection
Start date: 2020-03-17, end date: 2020-03-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 772004374945
Unscheduled inspection
Start date: 2020-03-19, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection:


# 772004201054
Unscheduled inspection
Start date: 2020-01-16, end date: —, duration:
Authority:
Purpose of inspection:


# 771903978930
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility construction of metering devices for energy resources used


# 501903886627
Unscheduled inspection
Start date: 2019-10-23, end date: 2019-11-20, duration:
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: check


# 771903610205
Unscheduled inspection
Start date: 2019-09-18, end date: 2019-10-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit is to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and requirements for the equipment of the capital construction facility with metering devices for used energy resources


# 77190803455018
Unscheduled inspection
Start date: 2019-07-15, end date: 2019-07-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code


# 77190803399804
Unscheduled inspection
Start date: 2019-04-18, end date: 2019-05-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803367806
Unscheduled inspection
Start date: 2019-03-14, end date: 2019-03-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771902594658
Unscheduled inspection
Start date: 2019-03-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803324282
Unscheduled inspection
Start date: 2019-01-31, end date: 2019-02-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803316923
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-02-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803282337
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-12-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803254268
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 501800750362
Unscheduled inspection
Start date: 2018-09-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803233688
Unscheduled inspection
Start date: 2018-09-21, end date: 2018-10-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803187001
Unscheduled inspection
Start date: 2018-07-26, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803142499
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 501800203804
Unscheduled inspection
Start date: 2018-03-19, end date: —, duration:
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Moskovskoi oblasti
Purpose of inspection:


# 77180803109647
Unscheduled inspection
Start date: 2018-03-28, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803091614
Unscheduled inspection
Start date: 2018-02-27, end date: 2018-03-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803081963
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803066450
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802788066
Unscheduled inspection
Start date: 2017-10-30, end date: 2017-11-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used