Found 5 inspections:

# 772100536875
Unscheduled inspection
Start date: 2021-08-26, end date: 2021-09-08, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor


# 772100263783
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-30, duration: 17
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision


# 772005147234
Unscheduled inspection
Start date: 2020-10-07, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 50170802983299
Unscheduled inspection
Start date: 2017-12-08, end date: 2017-12-19, duration:
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: inspections of the elimination of violations notification of the elimination of violations P00188017945649511132 dated 23112017 within the framework of regulation 0908030405504 dated 19102017 with a deadline of up to 30112017 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility Multi-apartment residential building with built-in premises at 143980 Moscow region Zheleznodorozhny MKR Center 2 Quarter 2a cor 211


# 50170802983274
Unscheduled inspection
Start date: 2017-12-08, end date: —, duration:
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.