Found 3 inspections:

# 742201503930
Unscheduled inspection
Start date: 2022-01-28, end date: 2022-02-03, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the work performed on the foundations of the hydraulic fracturing building at the end of work; installation of supporting structures of the hydraulic fracturing building at the end of work; installation of enclosing structures and the roof of the hydraulic fracturing building during construction; external power supply of hydraulic fracturing during construction; installation of gas pipelines in the MMK hydraulic fracturing area, from MMK hydraulic fracturing to GRSZ, from CHP to MMK hydraulic fracturing (installation of foundations, supporting structures, pipelines) during construction and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work, according to the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the design documentation in accordance with parts 3.8 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.


# 742101245316
Unscheduled inspection
Start date: 2021-10-29, end date: —, duration:
Authority:
Purpose of inspection:


# 742100435529
Unscheduled inspection
Start date: 2021-08-19, end date: 2021-08-25, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with site preparation work, installation of temporary passageways for the construction of the hydraulic fracturing plant, gas pipelines from the MMK hydraulic fracturing plant to the GRSZ, from the MMK hydraulic fracturing plant to the TPP hydraulic fracturing plant; installation of the foundations of the hydraulic fracturing plant during construction; installation of the gas pipeline from the MMK hydraulic fracturing plant to the GRSZ (installation of foundations, supporting structures, pipeline) during construction. and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.