Found 10 inspections:

# 782100103434
Unscheduled inspection
Start date: 2021-03-22, end date: 2021-04-16, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki rabot, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, o srokah zaversheniya rabot, kotorye podlezhat proverke vh. № 03-5066/2019-13 ot 25.02.2021 - montazh vnutrennih setei i sistem inzhenerno-tehnicheskogo obespecheniya; proverki zaversheniya rabot, predusmotrennyh programmoi provedeniya proverok delo № ZH11-05(19), № 03-5066/2019 ot 03 iyulya 2019 goda (montazh vnutrennih setei inzhenerno-tehnicheskogo obespecheniya - 01.03.2021, montazh inzhenernyh sistem i oborudovaniya - 01.02.2021); ) soblyudenie obyazatelnyh trebovanii, v tom chisle: sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichie razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii; b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti; v) provedenie meropriyatii: po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede; po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera; po likvidacii posledstvii prichineniya takogo vreda.


# 782100104382
Unscheduled inspection
Start date: 2021-02-15, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 472004486360
Unscheduled inspection
Start date: 2020-08-19, end date: —, duration:
Authority:
Purpose of inspection:


# 472004283752
Unscheduled inspection
Start date: 2020-02-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471902931035
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this check is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this check are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this check are to prevent identify and suppress the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and design documentation, The purpose of checking the elimination of violations of mandatory requirements specified in the notice of the person carrying out the construction on the elimination of violations identified, the subject of this check is compliance with mandatory requirements, including compliance with the performance of works and applied building materials during the construction reconstruction of the capital construction facility and also, the results of such work meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used meeting the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation


# 471902625102
Unscheduled inspection
Start date: 2019-04-03, end date: 2019-04-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471802078888
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-12-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 471800578092
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-08-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 47170701358519
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-03-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification. The purpose of this verification is to comply with mandatory requirements, including compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and equipment requirements for the capital construction facility accounting for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47170701326655
Unscheduled inspection
Start date: 2017-01-25, end date: 2017-02-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification. The purpose of this verification is to comply with mandatory requirements, including compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and equipment requirements for the capital construction facility accounting for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.