Found 17 inspections:

# 772004432584
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004329197
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904117182
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used


# 77190803468950
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803430049
Unscheduled inspection
Start date: 2019-06-04, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803167412
Unscheduled inspection
Start date: 2018-06-25, end date: 2018-07-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803099511
Unscheduled inspection
Start date: 2018-03-12, end date: 2018-03-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803067491
Unscheduled inspection
Start date: 2018-01-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802920943
Unscheduled inspection
Start date: 2017-11-29, end date: 2017-12-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802765852
Unscheduled inspection
Start date: 2017-10-24, end date: 2017-11-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: availability of a certificate of admission issued by a self-regulating organization to works that affect the safety of capital construction facilities, compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802470959
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701842443
Unscheduled inspection
Start date: 2017-07-31, end date: 2017-08-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701724182
Unscheduled inspection
Start date: 2017-06-21, end date: 2017-07-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701326271
Unscheduled inspection
Start date: 2017-01-26, end date: 2017-02-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701217360
Unscheduled inspection
Start date: 2016-12-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77160700112733
Unscheduled inspection
Start date: 2016-09-02, end date: 2016-09-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 740216 ot 22072016


# 77160601706221
Unscheduled inspection
Start date: 2016-07-20, end date: 2016-07-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.