# 162101322236
Unscheduled inspection
Start date: 2021-11-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100658880
Unscheduled inspection
Start date: 2021-09-13, end date: 2021-04-14, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of compliance of the performed works, applied in the process of construction (reconstruction) of the capital construction facility of building materials, the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of capital construction facilities with metering devices for energy resources used; verification of the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction, on the basis of a contract with the developer or the customer, of compliance with the requirements of the project documentation performed during the construction of the capital construction facility; compliance with mandatory requirements or requirements established by municipal legal acts.
# 162100311170
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 162100119440
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-14, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of compliance of the performed works, applied in the process of construction (reconstruction) of the capital construction facility of building materials, the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of capital construction facilities with metering devices for energy resources used; verification of the availability of a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation, prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction, on the basis of a contract with the developer or the customer, of compliance with the requirements of the project documentation performed during the construction of the capital construction facility; compliance with mandatory requirements or requirements established by municipal legal acts.