Found 3 inspections:

# 162101398755
Unscheduled inspection
Start date: 2021-11-30, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the construction of the capital construction facility, and the results of such work with the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 11/23/2021 case No. 13-11-2021/0054. The objectives of this audit are: prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility.


# 162005280851
Unscheduled inspection
Start date: 2020-12-17, end date: 2020-12-30, duration: 11
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine whether the construction materials used in the construction of a capital construction facility and the results of such work comply with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 16112020 case 131120200066the objectives of this inspection are to prevent, identify and prevent violations of compliance with technical regulations, other regulatory legal acts and project documentation7 carried out by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, with the requirements of technical regulations, other regulatory legal acts and project documentation7the subject of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by municipal legal acts


# 161902647698
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-04-05, duration:
Authority: Ministerstvo ekologii i prirodnyh resursov Respubliki Tatarstan
Purpose of inspection: This audit is conducted in order to verify the fulfillment of an order to eliminate violations of the requirements of environmental legislation issued based on the results of an audit dated 31052018. The deadline for the fulfillment of the regulations expires on 01032019. The subject of this audit is compliance with mandatory requirements of environmental legislation, regulatory legal acts, environmental standards rules and other regulatory documents on environmental protection by the person being audited


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.