Found 4 inspections:

# 661802016266
Unscheduled inspection
Start date: 2018-11-01, end date: 2018-11-29, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the KNM inspection is carried out on the basis of the notice of completion of the capital construction facility vh 29018245236 dated October 22, 2018 in accordance with the provisions of subparagraph "a" of paragraph 2 of Part 5 of Article 54 of the Urban Planning Code of the Russian Federation the objectives of this inspection are the implementation of regional state construction supervision, the subject of verification of the completed construction of the capital construction facility compliance with the work and applicable construction materials in the process of construction of the capital construction facility "Asphalt plant LLC PTM plus in Krasnoturinsk Correction 1" located at Sverdlovsk region Krasnoturinsk 235 m in the direction to the southeast from the landmark non-residential building located outside the site address of the landmark Krasnoturinsk Frunze street d78 the results of such work to the requirements of design documentation, including energy efficiency requirements and the requirements of equipping the capital construction facility with metering devices for energy resources used, as well as the availability of a construction permit and compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 661800362799
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-06-13, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: The purpose of the KNM inspection is carried out in order to implement the program of inspections from 14032018 2919019218 Tasks of the KNM implementation of state construction supervision The subject of the KNM verification of compliance with the performance of works and building materials used in the construction of the capital construction facility "Asphalt plant LLC "PTM plus" in Krasnoturinsk Correction 1" located at Sverdlovsk region Krasnoturinsk 235 meters in the direction of southeast of the landmark is a non-residential building located outside the site address of the landmark Sverdlovsk region Krasnoturinsk Frunze str. 78 the results of such work meet the requirements of technical regulations sanitary and epidemiological rules and regulations fire safety requirements safety rules and state standards of design documentation including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used as well as the availability of a permit for the construction and fulfillment of the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 66170701509680
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-05-10, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: verification of the completed construction of the capital construction facility for compliance with the performance of works and construction materials used in the construction of the capital construction facility "Asphalt plant LLC PTM Plus in Krasnoturinsk" located at the address Sverdlovsk region Krasnoturinsk 235 m in the direction to the southeast from the landmark non-residential building located outside the site address landmark Sverdlovsk region Krasnoturinsk Frunze street e 78 of the results of such work meet the requirements of technical regulations and design documentation, including energy efficiency requirements


# 66160701219676
Unscheduled inspection
Start date: 2016-12-12, end date: 2017-01-13, duration:
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To check the compliance of the work and the construction materials used in the construction of the capital construction facility "Asphalt plant LLC "PTM plus" in Krasnoturinsk" located at the address Sverdlovsk region Krasnoturinsk 235 m in the direction to the southeast from the landmark non-residential building located outside the site address landmark Sverdlovsk region Krasnoturinsk ul Frunze d 78 the results of such works according to the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for used energy resources


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.