Found 2 inspections:

# 332101371071
Unscheduled inspection
Start date: 2021-11-11, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora administracii Vladimirskoi oblasti
Purpose of inspection: - verification of the compliance of the work performed and the construction materials and products used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (including taking into account the changes made to the working documentation and which are in accordance with part 1.3 of Article 52 of this Code as part of such project documentation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code) - checking for a building permit; - verification of compliance with the requirements of Parts 2, 3.1 of art. 52 of the Urban Planning Code of the Russian Federation; - verification of compliance with the requirements of Part 4 of Article 52 of this Code to ensure the conservation of the capital construction facility; - verification of compliance with the requirements for the construction control procedure established by this Code and other regulatory legal acts The subject of this audit is: compliance with mandatory requirements and/or requirements established by municipal legal acts.


# 332100513310
Unscheduled inspection
Start date: 2021-08-26, end date: —, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora administracii Vladimirskoi oblasti
Purpose of inspection: Objectives: to verify the implementation of the notice of elimination of the violation dated 08/13/2021. Tasks: verification of compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of regulatory legal acts, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources; verification of the availability of a construction permit; verification of compliance with the requirements of parts 2, 3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation; compliance with the requirements of the high-readiness regime. Subject: compliance with mandatory requirements and/or requirements established by municipal legal acts.


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.