Found 12 inspections:

# 001904114046
Unscheduled inspection
Start date: 2019-12-19, end date: —, duration:
Authority:
Purpose of inspection:


# 001904113874
Unscheduled inspection
Start date: 2019-12-19, end date: 2019-12-23, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction of the Caucasian Rostechnadzor Office dated 28102019 5709RPA18 on the elimination of violations by LLC Grand during the construction of the reconstruction of a capital construction facility. The objectives of this audit are to monitor the measures taken by LLC Grand to comply with the instruction of the Caucasian Rostechnadzor Office dated 28102019 5709RPA18 and compliance with mandatory requirements of regulatory acts in the field of construction when During the construction and reconstruction of a capital construction facility, the subject of this audit is to note the necessary fulfillment of the instructions of the state control and supervision authorities


# 302101403402
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: THE PURPOSE IS TO CHECK THE INSTALLATION OF EXTERNAL AND INTERNAL SYSTEMS, BUILDING EQUIPMENT, BASED ON A NOTICE OF COMPLETION DATES TO BE CHECKED DURING THE CONSTRUCTION OF THE ACS - The construction of a kindergarten for 330 places on Song Yat-Sen/Markin St./Socialist village of Dargomyzhsky in the Leninsky district of Astrakhan; THE TASK IS TO VERIFY THE COMPLIANCE OF THE COMPLETED WORKS WITH THE REQUIREMENTS OF THE DESIGN DOCUMENTATION DURING THE CONSTRUCTION OF THE ACS; THE SUBJECT OF THE KNM IS COMPLIANCE WITH MANDATORY REQUIREMENTS.


# 302101343923
Unscheduled inspection
Start date: 2021-11-02, end date: —, duration:
Authority:
Purpose of inspection:


# 302100678902
Unscheduled inspection
Start date: 2021-09-02, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: Execution of the order of the service dated 08/02/2021 No. 1 OKS-Construction of a 192-apartment residential building on Bulvarnaya Street in the Leninsky district of Astrakhan


# 302101210278
Unscheduled inspection
Start date: 2021-09-01, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: Execution of the order of the service dated 08/02/2021 No. 1 OKS-Construction of a kindergarten for 330 places on Sun Yat-Sen/Markina St./Socialist village of Dargomyzhsky in the Leninsky district of Astrakhan


# 302101237577
Unscheduled inspection
Start date: 2021-07-09, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: INSPECTION OF COMPLETED WORKS, ACCORDING TO THE INSPECTION PROGRAM FOR THE CONSTRUCTION OF THE ACS – The construction of a kindergarten for 330 places on Sun Yat-Sen/Markin St./Socialist village of Dargomyzhsky in the Leninsky district of Astrakhan


# 302101148866
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: NOTICE OF COMPLETION DATES FOR the construction of a 192-apartment apartment building on Bulvarnaya St. in the Leninsky district of Astrakhan


# 002004434586
Unscheduled inspection
Start date: 2020-06-18, end date: 2020-06-19, duration: 2
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction of the Caucasian Rostechnadzor Office dated 28052020 RP4109670 on the elimination of violations by LLC Grand during the construction of the reconstruction of a capital construction facility. The objectives of this audit are to monitor the measures taken by LLC Grand to comply with the instruction of the Caucasian Rostechnadzor Office dated 28052020 RP4109670 and compliance with mandatory requirements of regulatory acts in the field of construction During the construction and reconstruction of a capital construction facility, the subject of this audit is the fulfillment of the instructions of the state control and supervision authorities.


# 201904057770
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-02, duration:
Authority: Gosudarstvennyi komitet po arhitekture i gradostroitelstvu CHechenskoi Respubliki
Purpose of inspection: verification of compliance with the requirements of current legislation in the field of construction, fire safety, sanitary and epidemiological welfare, compliance with norms and rules in the field of environmental protection, energy efficiency requirements and equipment with metering devices for consumed resources during the construction of facilities


# 001904114046
Unscheduled inspection
Start date: 2019-12-19, end date: 2019-12-23, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction of the Caucasian Rostechnadzor Department dated 06122019 6378RVA18 on the elimination of violations by LLC Grand during the construction of the reconstruction of a capital construction facility. The objectives of this audit are to monitor the measures taken by LLC Grand to comply with the instruction of the Caucasian Rostechnadzor Department dated 06122019 6378RVA18 and compliance with mandatory requirements of regulatory acts in the field of construction when During the construction and reconstruction of a capital construction facility, the subject of this audit is the fulfillment of the instructions of the state control and supervision authorities


# 001904113874
Unscheduled inspection
Start date: 2019-12-19, end date: 2019-12-23, duration:
Authority: Kavkazskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to monitor the implementation of the previously issued instruction of the Caucasian Rostechnadzor Office dated 28102019 5709RPA18 on the elimination of violations by LLC Grand during the construction of the reconstruction of a capital construction facility. The objectives of this audit are to monitor the measures taken by LLC Grand to comply with the instruction of the Caucasian Rostechnadzor Office dated 28102019 5709RPA18 and compliance with mandatory requirements of regulatory acts in the field of construction when During the construction and reconstruction of a capital construction facility, the subject of this audit is to note the necessary fulfillment of the instructions of the state control and supervision authorities


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.